Industrial Development

Dáil Éireann Debate, Tuesday - 30 January 2024

Tuesday, 30 January 2024

Questions (242, 243)

Alan Dillon

Question:

242. Deputy Alan Dillon asked the Minister for Enterprise, Trade and Employment if he will identify the locations and completion date for each Advanced Building Solutions delivered under the IDA regional building programme; and if he will make a statement on the matter. [3919/24]

View answer

Alan Dillon

Question:

243. Deputy Alan Dillon asked the Minister for Enterprise, Trade and Employment if he will identify each location for outstanding Advanced Building Solutions and current project lifecycle phase, ii.e., site selection, design, planning process, etc., in tabular form, for each of the outstanding Advanced Building Solutions under the IDA regional building programme; and if he will make a statement on the matter. [3920/24]

View answer

Written answers

I propose to take Questions Nos. 242 and 243 together.

As the deputy is aware, Government policy and the IDA strategy both recognise that the timely provision of appropriate, innovative, and cost-effective property solutions that meet the needs of multinational companies at the forefront of a modern economy remains essential to winning FDI.  A robust property and infrastructure ecosystem can be the key differentiator in winning FDI projects. 

The IDA Regional Property Programme ensures the supply of land, buildings and essential infrastructure in regional locations as required by current and prospective clients of IDA as well as those of Enterprise Ireland and the Local Enterprise Offices. Under its current strategy, ‘Driving Recovery and Sustainable Growth 2021–2024’, IDA is progressing delivery of 19 Advanced Building Solutions (ABS) in regional locations.  

Delivery of the IDA Regional Property Programme is dependent on a wide range of external stakeholders and FDI client timelines.  Many factors impact on timelines, and capital-intensive property investment projects by their very nature run over multiple years. Against the backdrop of the difficulties experienced in the construction sector globally and despite the impact of Covid and construction price inflation on both works & budgets, IDA has maintained momentum on the delivery of its Regional Property Programme. 

Eight properties have been completed since the start of the current strategy. The locations and completion date for each of these is set out in Table 1 below:

Table 1

Building Name

Location

Completion Period

Dundalk AOB

Finnabair Business Park, Dundalk, Co Louth

Q3 2022

Sligo AOB

Sligo Business & Technology Park, Finisklin

Q4 2021

Monaghan ABS

Monaghan Business & Technology Park

Q3 2021

Limerick ABS

Raheen Business Park, Limerick

Q4 2022

Limerick AMC

National Technology Park, Limerick

Q4 2021

Waterford ABS

Waterford Business & Technology Park, Butlerstown, Waterford

Q1 2023

Carlow ABS

IDA Business & Technology Park, Dublin Road, Carlow

Q4 2023

Athlone ABS

Athlone Business & Technology Park, Westmeath

Q4 2023

Additionally, there are 11 further buildings being progressed under the IDA Building Programme which are listed in Table 2 below:

Table 2

Building Name

Location

Completion Stage

Sligo ABS

Oakfield Business Park, Sligo

Under Construction

Galway ABS 2

Parkmore, Galway

Under Construction

Athlone AF4

Garrycastle, Athlone

Under Construction

Mullingar ABS

Mullingar, Co Westmeath

Contract Procurement Stage

Cavan ABS

Cavan

Contract Procurement Stage

Letterkenny ABS

Letterkenny, Co Donegal

Planning Stage

Drogheda ABS

Drogheda, Co Louth

Planning Stage

Tralee

Tralee, Co Kerry

Design Stage & Planning

Longford ABS

Longford

Site Identification

Oranmore

Galway

Site Identification

Castlebar

Castlebar, Co Mayo

Site Identification

Many factors impact on timelines for the delivery of construction projects including, site identification, willing vendors, planning, procurement & a variety of macro-economic factors.

In that regard, the construction industry continues to be impacted by global supply chain and cost inflation challenges. IDA Property Division continues to monitor these challenges and the impact of same on the delivery of the regional property programme. IDA will use its best endeavours to deliver all buildings in a timely manner.

Question No. 243 answered with Question No. 242.