Housing Provision

Dáil Éireann Debate, Thursday - 15 February 2024

Thursday, 15 February 2024

Questions (105)

Matt Carthy

Question:

105. Deputy Matt Carthy asked the Minister for Housing, Local Government and Heritage the number of social and affordable homes delivered in County Monaghan in the years 2020, 2021, 2022 and 2023; and the number targeted to built in 2024. [6882/24]

View answer

Written answers

Housing for All is the Government’s plan to increase the supply of housing to an average of 33,000 per year over the next decade. This includes the delivery of 90,000 social homes, 36,000 affordable purchase homes and 18,000 cost rental homes. Housing for All is supported by an investment package of over €4bn per annum, through an overall combination of €12bn in direct Exchequer funding, €3.5bn in funding through the Land Development Agency and €5bn funding through the Housing Finance Agency.

My Department publishes comprehensive programme-level statistics on a quarterly basis on social housing delivery activity by local authorities and Approved Housing Bodies (AHBs) in each local authority. This data is available to the end of Q3 2023 and is published on the statistics' page of my Department’s website at the following link: gov.ie - Overall social and affordable housing provision (www.gov.ie)

Data for Q4 2023 is currently being collated and will be published shortly. Monaghan’s social housing build target for 2024 is 57.

My Department also publishes the Social Housing Construction Status Report (CSR). The CSR provides details of social housing developments and their location that have been completed, are under construction or are progressing through the various stages of the design and tender processes. The most recent publication was for Quarter 3 2023. All Construction Status Reports are available at the following link: www.gov.ie/en/collection/cb885-social-housing-construction-projects-status-reports/

A version of the CSR file can also be downloaded for analysis of completions, locations, approvals stage etc. at this link: data.gov.ie/dataset/social-housing-construction-status-report-q3-2023

Monaghan County Council does not have affordable housing delivery target as the assessed level of affordably constrained need is not high, as house prices are below the national median. The Affordable Housing Fund (AHF) is available to all local authorities to assist in responding to localised affordability need where it occurs. Monaghan has not applied for AHF assistance to date. Assistance with developing schemes is available from my Department, the Housing Agency and the Local Government Management Agency if required.