1170. Deputy Carol Nolan asked the Minister for Children, Equality, Disability, Integration and Youth to provide an update on the provision of the 500 rapid build modular homes originally approved in June 2022 and later increased to 700 units for beneficiaries of temporary protection; if the initial estimated cost was €140 million for the project; the current overall cost to the nearest estimate and per unit; and if he will make a statement on the matter. [12548/24]

View answer

Written answers

As part of the State’s humanitarian response to the Ukrainian crisis, the government has developed a rapid build housing programme to provide accommodation for families fleeing the war in Ukraine. The programme aims to provide short-term accommodation up to 2,800 Ukrainians at several sites across Ireland. While rapid build units will initially be used to temporarily house people fleeing Ukraine, they have the potential to be utilised to address other accommodation challenges, including social housing and student accommodation.

This project – the first of its kind – is an important one as it will provide a blueprint for future developments. As each phase has brought new challenges, these challenges will provide important future learnings.

The emphasis in this programme is on delivery of quality homes which will enhance local environments and this has been a priority.

Each site will have roads, footpaths, street lighting, community facilities, including green spaces, fully in line with Local Authority planning guidance. The homes will be highly energy efficient, durable units with a 60 year lifespan and the development of the sites will be conducted in an environmentally sustainable way to ensure that, post development, the site will enhance the local area. Construction disruption is limited as the units are manufactured off site.

Work has been completed on the first seven sites (Mahon Cork, Farnham Road Cavan, Doorly Park Sligo, Thurles Tipperary, Claremorris Mayo, Clonminch Offaly and Rathdowney Laois). Residents have moved into six of the sites with the seventh site being occupied this week. By the end of this week 310 homes with a capacity to house 1240 will have been delivered and occupied. The final stage of the programme will be delivered in 2024.

The completion timelines are subject to any technical issues arising during construction. There were a number of such issues that arose over the past few months relating to site conditions, remedial works, boundaries, ESB connections, etc. that delayed earlier forecasted dates of completion on sites included in the programme.

The cost of each unit is approximately €145,000 per unit, inclusive of supply, delivery and provision of loose electrical and household items. This is separate to the site development and utility connection costs, etc. relating to the overall development. As the project is still ongoing and further sites are under consideration, it is not possible to fully specify a final overall programme figure at this time.

Question No. 1171 answered with Question No. 1088.