285. Deputy Colm Burke asked the Minister for Public Expenditure, National Development Plan Delivery and Reform when a project (details supplied) which was granted planning permission in 2022 can proceed; if this project has been advertised in order that tenders can be submitted; when is it likely that the tender process will be completed; and if he will make a statement on the matter. [11858/24]

View answer

Written answers

The Department of Transport and the Irish Coast Guard are responsible for the financing of Coast Guard station projects. The Office of Public Works is responsible for site acquisition, design, construction and delivery of these projects on behalf of D/Transport and ICG.

In late 2022, the OPW secured planning permission for a new coast guard station at Castlefreke. The OPW is now in the detailed design phase of the project and in the process of preparing tender documentation. It is anticipated that this project will be tendered in the second half of 2024 and that a contract will be placed before the end of the year.

Top
Share