Schools Building Projects

Dáil Éireann Debate, Tuesday - 16 April 2024

Tuesday, 16 April 2024

Questions (350)

Brian Stanley

Question:

350. Deputy Brian Stanley asked the Minister for Education the status of progress on the proposed new school (details supplied); if the project is in the capital school building programme; and the projected timeline for construction. [16594/24]

View answer

Written answers

The project to which the Deputy refers, was approved funding as a large scale capital project. It is devolved for delivery to Laois and Offaly Education and Training Board (LOETB)

I am pleased to advise that the project is currently at stage 2b of the architectural design process (developed design). At this stage the design team will obtain the statutory planning approvals, prepare a set of fully detailed Tender documents, and prepare an accurate pre-tender cost plan.

Once these approvals are in place, the project can proceed to tender and construction in due course.

At this juncture, it is not possible to give a date for its completion.

LOETB as the devolved delivery body, will continue to engage directly with the school authority to keep it informed of progress.