Schools Building Projects

Dáil Éireann Debate, Wednesday - 17 April 2024

Wednesday, 17 April 2024

Questions (59)

Jim O'Callaghan

Question:

59. Deputy Jim O'Callaghan asked the Minister for Education if, in regard to her press release of 10 April 2024, which references that 800 school building projects have been completed since 2020 and 300 other projects are under construction, she will detail the number of school building projects that have been completed, by county, in tabular form; to provide a breakdown of the total number of projects under construction, per county; and if she will make a statement on the matter. [17064/24]

View answer

Written answers

Since 2020, my department has invested in the region of €4.5 billion in our schools throughout the country, involving the completion of over 800 school building projects and with construction currently underway at approximately 300 other projects, which includes 31 new school buildings.   

These 300 projects currently at construction involve a total State investment of over €1.2bn.   

It is also planned that close to 90 projects currently at tender stage, including 28 new school buildings, will be authorised to proceed to construction over the course of 2024 and early 2025.  In total, around €800 million will be invested in these projects under the department’s Large Scale Capital Programme and Additional Accommodation Scheme for essential classroom accommodation.  

These projects moving to construction in this next phase will add in the region of 200,000 m2 of additional and modernised permanent capacity across the school estate and involve 28 new school buildings and 61 extensions at existing buildings.  

These projects will help schools cater for growing populations in their areas and include 138 classrooms for children with special education needs, which is a key priority for Government.  

This is a record level of investment in school buildings.  It will expand the number of school places, significantly increase provision for special education and upgrade and modernise our school infrastructure. The impact of this will be felt in communities, right around the country. 

The status of all school building projects, including those that are complete and in construction, is listed on a county by county basis at: www.gov.ie/en/service/c5b56b-major-projects/

The list is updated on a regular basis.  

Please see table below detailing number of projects completed and in construction by county.

County 

Total projects completed  

School Building Projects in Construction 

2020-2023 

Carlow 

16 

Cavan 

15 

Clare 

13 

10 

Cork 

104 

25 

Donegal 

35 

25 

Dublin 

169 

43 

Galway 

50 

27 

Kerry 

25 

Kildare 

26 

14 

Kilkenny 

32 

Laois 

19 

Leitrim 

Limerick 

27 

11 

Longford 

Louth 

21 

Mayo 

40 

14 

Meath 

40 

16 

Monaghan 

13 

Offaly 

21 

Roscommon 

15 

Sligo 

13 

Tipperary 

41 

17 

Waterford 

14 

Westmeath 

23 

Wexford 

39 

11 

Wicklow 

28 

Grand Total 

852 

292 