Skip to main content
Normal View

International Protection

Dáil Éireann Debate, Tuesday - 14 May 2024

Tuesday, 14 May 2024

Questions (538)

Donnchadh Ó Laoghaire

Question:

538. Deputy Donnchadh Ó Laoghaire asked the Minister for Children, Equality, Disability, Integration and Youth the average completion deadline for State-owned modular units dedicated to accommodating beneficiaries of temporary protection; the providing a breakdown of the average completion timelines for units procured in each of the years 2022, 2023 and to date in 2024; and the breakdown of the average completion timelines of units procured by county, in tabular form. [21852/24]

View answer

Written answers

Modular proof of concept sites

Columb Barracks, in Mullingar, County Westmeath, was selected by Government in 2023 as 1 of 5 ‘proof of concept sites’ in order to examine the potential of rapid build ‘pod’ style accommodation.

My Department has been working as part of the Accommodation Working Group under the auspices of the Department of the Taoiseach to advance the requirements needed in order to place the ‘pods’ on this site in a timely fashion. Works commenced on this site in April 2023.

The first 49 pods have been filled by Ukrainian families. The first 20 units were occupied in December 2023 with a further 29 families being accommodated during February 2024. The remaining units are expected to be ready and occupied in May 2024, including 3 wheelchair accessible units, bringing the site to full occupancy with 62 families.

As the site is still being finalised, it is not possible to provide the information in the manner requested by the Deputy.

Rapid Build sites

As part of the State’s humanitarian response to the Ukrainian crisis, the Government has developed a Rapid Build Housing Programme to provide accommodation for families fleeing the war in Ukraine who request it. The programme aims to provide short-term accommodation for up to 2,800 Beneficiaries of Temporary Protection (BOTPs) at several sites across Ireland. The Office of Public Works (OPW) is leading the development of this accommodation in conjunction with my Department.

The programme is being progressed under the emergency derogations from planning that were provided for by Government under S.I. No. 306 of 2022 – European Union (Planning and Development) (Displaced Persons from Ukraine Temporary Protection) Regulations, 2022.

The completion timelines are subject to any technical issues arising during construction. There were a number of issues that arose relating to site conditions, remedial works, boundaries, ESB connections. This delayed earlier forecasted dates of completion on sites included in the programme.

My Department does not collate the information in the manner requested by the Deputy in relation to the average completion deadline for State-owned modular units and the average completion timelines for units procured in each of the years 2022, 2023 and to date in 2024. Below set out in tabular form, is a breakdown of the completion dates by phases and by county.

Breakdown by phases

Phase 1 Sites

Start Date

Finish Date

Ballinure Way, Mahon, Cork

25/10/22

31/05/23

Doorly Park, Sligo

30/11/22

07/07/23

Cluain Ard, Claremorris, Co. Mayo

30/11/22

21/07/23

Gortataggart Way, Thurles, Co. Tipperary

23/11/22

16/08/23

Kilian Place, Farnham Rd, Cavan

10/11/22

25/08/23

Phase 1 average completion time: 244.8 days

Phase 2 Sites

Start Date

Finish date

Spring Crescent, Rathdowney, Co. Laois

27/03/23

06/12/23

Clonminch Place, Clonminch, Tullamore

27/03/23

21/11/23

Phase 2 average completion time: 246.5 days

Phase 3 Sites

Start date:

Target finish date

Stonewell, Backweston, Co. Dublin

10/07/23

08/07/24

Rathgoggan Way, Charleville, Co. Cork

17/07/23

02/08/24

Phase 3 average completion time based on target completion dates: 373 days

Phase 4 Sites

Start date

Target finish date

Cluain Buí, Pollboy, Ballinasloe

29/08/23

02/08/24

Clonmel, Tipperary

Mid May 2024

Feb 2025

Phase 4 average completion time based on target completion dates: N/A as start date has not commenced for all sites

Breakdown by county

An average completion timelines of units procured by county is provided below, where applicable.

Cork

Site name

Start Date

Finish date/Target Finish Date

Ballinure Way, Mahon, Cork

25/10/22

31/05/23

Rathgoggan Way, Charleville, Co. Cork

17/07/23

02/08/24

Co. Cork average estimated average completion time: 300 days

Sligo

Site name

Start Date

Finish date

Doorly Park, Sligo

30/11/22

07/07/23

Co. Sligo completion time: 219 days

Mayo

Site name

Start Date

Finish date

Cluain Ard, Claremorris, Co. Mayo

30/11/22

21/07/23

Co. Mayo completion time: 233 days

Tipperary

Site name

Start Date

Finish date/Target Finish Date

Gortataggart Way, Thurles, Co. Tipperary

23/11/22

16/08/23

Clonmel, Tipperary

Mid May 2024

Feb 2025

Co Tipperary average completion time: N/A as start date has not commenced for all sites

Cavan

Site name

Start Date

Finish date

Kilian Place, Farnham Rd, Cavan

10/11/22

25/08/23

Co Cavan completion time: 288 days

Laois

Site name

Start Date

Finish date

Spring Crescent, Rathdowney, Co. Laois

27/03/23

06/12/23

Co Laois completion time: 254 days

Offaly

Site name

Start Date

Finish date

Clonminch Place, Clonminch, Tullamore

27/03/23

21/11/23

Co. Offaly completion time: 239 days

Dublin

Site name

Start Date

Target Finish Date

Stonewell, Backweston, Co. Dublin

10/07/23

08/07/24

Co Dublin estimated completion time: 364 days

Galway

Site name

Start Date

Target Finish date

Cluain Buí, Pollboy, Ballinasloe

29/08/23

02/08/24

Co Galway estimated completion time: 339 days

Question No. 539 answered with Question No. 537.
Top
Share