Skip to main content
Normal View

Capital Expenditure Programme

Dáil Éireann Debate, Tuesday - 21 May 2024

Tuesday, 21 May 2024

Questions (419)

Catherine Murphy

Question:

419. Deputy Catherine Murphy asked the Minister for Justice to provide a breakdown of the amount of her Department's pre-committed capital expenditure under the National Development Plan that will be dedicated to An Garda Síochána capital building programme in each of the years 2024 to 2026, in tabular form. [22368/24]

View answer

Written answers

Following intensive negotiations with the Department of Public Expenditure, NDP Delivery and Reform, my Department has secured an additional €93m for capital projects across the Justice Sector bringing the total capital budget to €930m for the years 2024-2026.

The revised capital allocations for the Garda Vote are set out in the table below.

Year

An Garda Síochána Total Capital (Indicative Figures)

Garda Capital Building Programme (Indicative figures)

2024

€171.6m

€57.4m*

2025

€173.1m

€62.4m

2026

€172.3m

€65.8m

* As published in Revised Estimates Volume 2024

Top