asked the Minister for Local Government if he will state in respect of each of the recently completed housing schemes at (i) Rathkeale, (ii) Croom, (iii) Bruree, (iv) Cappamore, County Limerick, (a) when the site was acquired, (b) when the contract was made, (c) when building work was started, (d) what was the all-in cost per house, and (e) what is the rent fixed per house.
Ceisteanna—Questions. Oral Answers. - County Limerick Housing Schemes.
The information required by the Deputy is in the form of a tabular statement which, with the permission of the Ceann Comhairle, will be circulated in the Official Report.
The following is the statement:—
Scheme |
When the site was acquired |
When the contract was made |
When building work started |
All-in cost per house (including land acquisition and development costs) |
Rent fixed per house (a sum for rates is payable in addition) |
£ |
|||||
Rathkeale |
1934 |
6/10/47 |
8/10/47 |
1,067 |
6/- per week |
Croom |
1938 |
26/1/48 |
9/2/48 |
1,376 |
6/- ,, |
Bruree |
1938 |
12/4/48 |
19/4/48 |
1,245 |
5/- ,, |
Cappamore |
1937 |
24/5/48 |
28/5/48 |
1,233 |
5/- ,, |