Ceisteanna—Questions. Oral Answers. - Local Authority Housing.

asked the Minister for Local Government if he will state the particulars requested as regards local authority housing in Question No. 42 of the 25th March, 1952, for the months of February and March, 1952.

As the reply is in the form of a tabular statement, I propose, with your permission, a Cheann Comhairle, to circulate it with the Official Report.

Following is the information:—

LOCAL AUTHORITY HOUSING.

Number of Houses

Number of men employed

Date

In progress

For which tenders had been accepted or invited

For which Site Development was in progress

For which Sites had been acquired but no development work commenced

Skilled

Total

29/2/52

9,459

2,811

1,562

9,278

5,105

10,776

31/3/52

9,526

3,158

1,626

8,699

5,109

11,128

asked the Minister for Local Government if he will state in respect of local authority housing the number of dwellings completed in February and March, 1952, respectively, and the total erected in the years ending 31st March, 1951 and 1952.

The numbers of dwellings completed by local authorities during the months of February and March, 1952, were 473 and 721 respectively. The total numbers completed in the years ending 31st March, 1951, and 1952, were 7,787 and 7,195 respectively.