I propose, with your permission, a Cheann Comhairle, to take questions Nos. 17 and 18 together.
I assume that the school to which the Deputy refers as Bonmahon is Knockmahon, Bonmahon, Co. Waterford.
A grant was sanctioned by my Department on the 15th July, 1954 towards the cost of erecting the proposed school.
I am advised by the Commissioners of Public Works, who arranged for the building of the school, that work on its erection commenced on 23rd April, 1956.
The original contract provided for dry latrines but when the school was in course of construction a well which provided an adequate supply of water was sunk near the school site and a request was then made to the Commissioners of Public Works by the Manager for the installation of a water-flushed system of sanitation.
This necessitated the preparation of fresh working drawings and a specification and consequently the work of erecting the school was held up. When building work was resumed subsequently the builder failed to complete his contract.
Consequent on this it was necessary for the Commissioners of Public Works to prepare fresh drawings and a specification with a view to the invitation of tenders for the completion of the school. A second contract has been placed and the erection of the building is nearing completion.
As the original contract provided for dry latrines it was not necessary to have plans and specifications provided for the electric pumping of the well at the start of building.
The Commissioners of Public Works do not provide for the installation of electric lighting in national schools unless a request is made for its provision by the Manager. In the case of this school the Manager applied for the installation of electric lighting on the 22nd April, 1959. A specification therefor was prepared by the Commissioners and tenders were invited on 1st July, 1959. The latest date for the acceptance of tenders is 14th July, 1959.
The Commissioners of Public Works expect to have the school completed and the electrical installation provided for lighting and the pumping of water by the 31st August, 1959, and so the school should be ready for occupation when the summer holidays expire.