asked the Minister for Transport and Power if he will state the priority order fixed by the ESB under the planned post development scheme in south and east Kerry in the order of districts; and the respective date by which each district will be served.
Ceisteanna—Questions. Oral Answers. - Kerry Rural Electrification.
The information requested by the Deputy is in the form of a tabular statement which, with your permission, a Cheann Comhairle, I propose to circulate with the Official Report.
Following is the statement:
The undermentioned seven areas are due for re-canvass under the present Planned Post Development Programme as follows:
Killorglin |
Late |
1971 |
Kilgarvan |
Mid |
1972 |
Templenoe |
Late |
1972 |
Tuosist |
Early |
1973 |
Sneem |
Late |
1973 |
Caherdaniel and Mastergeehy |
Mid |
1974 |
Waterville |
Early |
1975 |
In line with the current plans for the completion of the Rural Electrification Scheme by 1975, advertisements will be published in the local papers inviting interested parties in the following areas to apply for connection. The present schedule for the order of development in these areas is:—
Milltown |
Early |
1972 |
Firies |
Early |
1972 |
Keel |
Mid |
1972 |
Beaufort |
Mid |
1972 |
Aghadoe |
Mid |
1972 |
Glenflesk |
Late |
1972 |
Barraduff |
Late |
1972 |
Gneeveguilla |
Late |
1972 |
Shinnagh |
Early |
1973 |
Glenbeigh |
Late |
1974 |
Caherciveen |
Late |
1974 |
Portmagee |
Late |
1974 |
The time taken to complete work in each area will depend on the number of acceptances but on average it is expected that it will take approximately three months to complete the development work in each area.