Skip to main content
Normal View

Dáil Éireann debate -
Tuesday, 2 Dec 1975

Vol. 286 No. 4

Ceisteanna—Questions. Oral Answers. - County Cork Pier.

19.

asked the Minister for Finance whether the Office of Public Works have yet reported to the Department of Agriculture and Fisheries on the condition of the pier at West End, Bere Island, County Cork, as requested on the 24th June, 1974; and if he will make a statement on the matter.

Because of many other urgent commitments the Commissioners of Public Works have not been in a position to prepare an engineering report on the pier at West End, Bere Island. However, I am arranging to have the report expedited.

Would the Parliamentary Secretary agree that 18 months is a long time to be awaiting a report from his Department in respect of inspection of a pier at Bere Island particularly when it only involves a few days work for one man?

As I have indicated, I am arranging that the report be expedited immediately.

Top
Share