17.

asked the Minister for the Environment to indicate the number of provincial towns located on the national primary route system which have current proposals for a by-pass; if he will indicate the following information in relation to each named town; the length of the proposed by-pass, the estimated cost of the by-pass, the length of time required to construct the by-pass, the approximate level of employment which will be created during the construction of the by-pass and the present state of outline or design proposals for each by-pass in question.

As the reply is in the form of a tabular statement, I propose, with the permission of the Ceann Comhairle, to circulate it with the Official Report.

Following is the statement:

Town

Length of proposed by-pass (approximate) Km.

Estimated cost of by-pass £ millions

Length of time required to construct by-pass (approximate)

Approximate level of employment which will be created during construction of by-pass

Present state of outline or design proposals

Athlone

7.65

7.0

6 years

not known

Alternative lines for by-pass being considered.

Arklow

6.4

1.7

3 years

not known

Outline plans prepared. Investigations regarding proposed bridge being undertaken by road authority.

Ballinasloe

not known

not known

not known

not known

By-pass route under consideration by road authority.

Birdhill

1.0

not known

not known

not known

Outline plans prepared. Road authority carrying out further examination of route.

Carlow

1st leg (Pollerton—Tullow Road)

0.78

0.135

2 years

not known

Under construction—scheduled for completion 1979.

2nd leg (Extension of N80)

0.88

0.353

3 years

not known

Plans approved and most of the necessary land is on the Council ownership.

Carrick-on-Shannon

not known

not known

not known

not known

Alternative lines for by-pass being considered.

Castleisland

3.0

0.6

2 years

not known

Preliminary design under consideration by road authority.

Collooney/Strandhill

not known

not known

not known

not known

By-pass route under consideration by road authority.

Dungarvan

3.3

not known

not known

not known

Line of proposed by-pass being considered.

Dunleer

not known

not known

not known

not known

Alternative lines for by-pass being examined.

Ennis

not known

not known

not known

not known

Survey being carried out by road authority to determine line of by-pass.

Galway (Corrib Bridge & Approaches)

1.6

2.25

3 years

not known

Application for Bridge order being processed.

Kilkenny

2.4

1.5

3 years

not known

Design in progress.

Killarney

3.0

0.5

2 years

not known

Preliminary design under consideration by road authority.

Leighlinbridge

not known

not known

not known

not known

Decision on by-pass line deferred pending determination of site of new bridge. Council asked to carry out soil investigations.

Letterkenny

0.6

0.150

3 years

not known

Under construction. Completion expected in 1979.

Lifford (Stranbane/Pluck)

0.61

0.160

2 years

not known

Limerick (Inner Ring Road)

1.2

0.75

2 years

not known

Part construction in progress. Railway overbridge being designed.

Longford

not known

not known

not known

not known

Alternative lines for by-pass under examination by road authority.

Mullingar

5.6

1.2

4 years

not known

Design work in progress.

Midleton

4.0

0.8

3 years

not known

Naas

8.0

6.0

4 years

not known

Report of public local inquiry into Motorway Scheme being considered.

Navan

2.40

0.8

4 years

not known

C.P.O. Inquiry concluded on 24 April 1979 and Inspector's report awaited.

Nenagh

not known

not known

not known

not known

By-pass route under examination by road authority.

New Ross

3.41

0.273

3 years

not known

Under construction (Completion expected 1980).

Newtownmountkennedy

not known

not known

not known

not known

Alternative lines for by-pass being considered.

Oranmore

3.0

0.6

2 years

not known

Preliminary design under consideration by road authority.

Roscrea

2.5

not known

not known

not known

Line of proposed by-pass being examined.

Thurles

2.8

not known

not known

not known

Wexford

9.1

1.78

5 years

not known

Part designed and land acquired—remainder being designed.

Would the Minister tell the House the number of towns?

There are five pages in the statement which deals with each town. There are approximately 30.

If a Minister is circulating a statement with the Official Report that should be sufficient without the House being held up answering questions about the contents of such statements.

Top
Share