asked the Minister for the Environment to indicate the number of provincial towns located on the national primary route system which have current proposals for a by-pass; if he will indicate the following information in relation to each named town; the length of the proposed by-pass, the estimated cost of the by-pass, the length of time required to construct the by-pass, the approximate level of employment which will be created during the construction of the by-pass and the present state of outline or design proposals for each by-pass in question.
Ceisteanna—Questions. Oral Answers. - By-Pass Road Proposals.
As the reply is in the form of a tabular statement, I propose, with the permission of the Ceann Comhairle, to circulate it with the Official Report.
Following is the statement:
Town |
Length of proposed by-pass (approximate) Km. |
Estimated cost of by-pass £ millions |
Length of time required to construct by-pass (approximate) |
Approximate level of employment which will be created during construction of by-pass |
Present state of outline or design proposals |
Athlone |
7.65 |
7.0 |
6 years |
not known |
Alternative lines for by-pass being considered. |
Arklow |
6.4 |
1.7 |
3 years |
not known |
Outline plans prepared. Investigations regarding proposed bridge being undertaken by road authority. |
Ballinasloe |
not known |
not known |
not known |
not known |
By-pass route under consideration by road authority. |
Birdhill |
1.0 |
not known |
not known |
not known |
Outline plans prepared. Road authority carrying out further examination of route. |
Carlow |
|||||
1st leg (Pollerton—Tullow Road) |
0.78 |
0.135 |
2 years |
not known |
Under construction—scheduled for completion 1979. |
2nd leg (Extension of N80) |
0.88 |
0.353 |
3 years |
not known |
Plans approved and most of the necessary land is on the Council ownership. |
Carrick-on-Shannon |
not known |
not known |
not known |
not known |
Alternative lines for by-pass being considered. |
Castleisland |
3.0 |
0.6 |
2 years |
not known |
Preliminary design under consideration by road authority. |
Collooney/Strandhill |
not known |
not known |
not known |
not known |
By-pass route under consideration by road authority. |
Dungarvan |
3.3 |
not known |
not known |
not known |
Line of proposed by-pass being considered. |
Dunleer |
not known |
not known |
not known |
not known |
Alternative lines for by-pass being examined. |
Ennis |
not known |
not known |
not known |
not known |
Survey being carried out by road authority to determine line of by-pass. |
Galway (Corrib Bridge & Approaches) |
1.6 |
2.25 |
3 years |
not known |
Application for Bridge order being processed. |
Kilkenny |
2.4 |
1.5 |
3 years |
not known |
Design in progress. |
Killarney |
3.0 |
0.5 |
2 years |
not known |
Preliminary design under consideration by road authority. |
Leighlinbridge |
not known |
not known |
not known |
not known |
Decision on by-pass line deferred pending determination of site of new bridge. Council asked to carry out soil investigations. |
Letterkenny |
0.6 |
0.150 |
3 years |
not known |
Under construction. Completion expected in 1979. |
Lifford (Stranbane/Pluck) |
0.61 |
0.160 |
2 years |
not known |
” |
Limerick (Inner Ring Road) |
1.2 |
0.75 |
2 years |
not known |
Part construction in progress. Railway overbridge being designed. |
Longford |
not known |
not known |
not known |
not known |
Alternative lines for by-pass under examination by road authority. |
Mullingar |
5.6 |
1.2 |
4 years |
not known |
Design work in progress. |
Midleton |
4.0 |
0.8 |
3 years |
not known |
” |
Naas |
8.0 |
6.0 |
4 years |
not known |
Report of public local inquiry into Motorway Scheme being considered. |
Navan |
2.40 |
0.8 |
4 years |
not known |
C.P.O. Inquiry concluded on 24 April 1979 and Inspector's report awaited. |
Nenagh |
not known |
not known |
not known |
not known |
By-pass route under examination by road authority. |
New Ross |
3.41 |
0.273 |
3 years |
not known |
Under construction (Completion expected 1980). |
Newtownmountkennedy |
not known |
not known |
not known |
not known |
Alternative lines for by-pass being considered. |
Oranmore |
3.0 |
0.6 |
2 years |
not known |
Preliminary design under consideration by road authority. |
Roscrea |
2.5 |
not known |
not known |
not known |
Line of proposed by-pass being examined. |
Thurles |
2.8 |
not known |
not known |
not known |
” |
Wexford |
9.1 |
1.78 |
5 years |
not known |
Part designed and land acquired—remainder being designed. |
Would the Minister tell the House the number of towns?
There are five pages in the statement which deals with each town. There are approximately 30.
If a Minister is circulating a statement with the Official Report that should be sufficient without the House being held up answering questions about the contents of such statements.