Written Answers. - INTERREG II Funding.

Brendan Smith

Question:

428 Mr. B. Smith asked the Minister for Transport, Energy and Communications the total funding available to his Department under the INTERREG II Programme; the projects assisted to date; the level of expenditure per project; the projects that will be assisted for the remainder of the programme; the level of funding per project; and if he will make a statement on the matter. [14369/96]

Under INTERREG II, a total investment programme of £30 million is proposed in the development of telecommunications, electricity and public transport.

The information requested by the Deputy is set out in the following table:

INTERREG II

Location

Description of Project

EU Aid

Total Cost

Implementation

Expenditure to date

£million

£million

£million

Public Transport

Dundalk

Enhance and enlarge bus station and development of travel centre

0.175

0.35

Feb-Aug 1997

Nil

Letterkenny

New passenger waiting area at bus station

0.085

0.17

Sept-Dec 1996

Nil

Drogheda

Improve passenger facilities at bus station and provide a travel centre

0.135

0.27

Feb-Aug 1997

Nil

Cavan

Improved passenger facilities at bus station including toilets for mobility impaired persons

0.075

0.15

Sept-Dec 1996

Nil

Development of Telecommunications

Cavan, Donegal, Leitrim, Louth and Monaghan

Exchange replacement and upgrading

3.2

6.4

1996-99

Nil

Cavan, Donegal, Louth, Monaghan and Sligo

Fibre optic cables with transmission systems

4.8

9.6

1996-99

Nil

Upgrading Electricity Network

Buncrana, County Donegal

Provision of Kv substation

1.8

3.6

1996-99

Nil

Dundalk, County Louth

Additional Transformer

0.85

1.7

1997-99

Nil

Lisdrum, County Monaghan

Additional Transformer

0.6

1.2

1995-96

0.794

Louth-Tandragee

Upgrading of metering and protection of interconnector

0.15

0.3

1996-99

Nil

Provision of new interconnector

2.63

5.26

1996-99

Nil

Promotion of Energy Efficiency

Border areas

“Energy Challenge” Scheme

0.5

1

1995-99

0.01

Overall Total

15

30