89 Mr. Power asked the Minister for Defence when the new accommodation planned for the Curragh will be available; and if he will make a statement on the matter. [4152/01]

The programme for the upgrading of facilities at the Curragh camp over the period 2000-05 consists of 22 projects. The target dates for completions in 2001 are as follows:

Project

EstimatedCompletion Date

Refurbishment of Hospital Wards for Accommodation

Completed

New Swimming Pool/Gymnasium

June 2001

General Accommodation Clarke Barracks

June 2001

Stores/Warehouses

June 2001

Coolmoney Camp refurbishment

July 2001

New Transport Technical Stores

August 2001

Connolly-Officers Mess conversion to Student Accommodation

September 2001

NCO's Mess, East

October 2001

Ordnance/Transport School

October 2001

Dining Complex NCO's Mess, West

October 2001

Workshops and Stores Plunkett/Connolly Barracks

November 2001

The remaining eleven projects are scheduled to be completed in the period 2002 to 2005.