Written Answers. - Departmental Programmes.

Dan Boyle

Question:

339 Mr. Boyle asked the Minister for Health and Children the moneys which have been expended in his Department by area and projects to date, under the RAPID and CLÁR programmes. [25858/02]

A major capital health project for an Alzheimer's disease day care centre at Kilgarven, County Kerry, is being funded at a total cost of €805,000 under the CLÁR programme. The Southern Health Board is providing €528,000 to the project. CLÁR funding, provided by the Department of Community Rural and Gaeltacht Affairs of €226,000 has been allocated, and the Alzheimer's Society has also raised €51,000 for the centre. Discussions are at present ongoing regarding the provision of additional CLÁR funding for other major capital health projects. A number of small capital projects relating to health service provision in CLÁR areas are also being funded under the CLÁR programme. The total cost of these projects is €2,613,311. The health boards are providing €1,906,275 and the balance of €707,036 is being provided by CLÁR funding. The attached schedule details the amount of CLÁR funding and the total amount of funding which has been allocated to each of these projects.

In relation to the RAPID programme, Government policy is that RAPID is to be funded through the prioritisation of the identified areas and the front loading to them of a significant share of the funding allocated under the national development plan. Agencies have been asked to implement the programme from within their existing resources. Officials from my Department have written to the RAPID co-ordinators and to the chief executive officers of the relevant health authorities to request that they prioritise the list of projects for their board, paying particular attention to the top five priorities. They are also asked to consider re-prioritisation that could be made on the basis of RAPID type projects from their 2002 allocation and which could be implemented within existing resources and to include as many prioritised RAPID proposals as possible in their service plans for 2003.
An internal group comprising representatives of relevant units within the Department of Health and Children has been established to ensure co-ordination with health board counterparts in service areas for which RAPID proposals have been submitted. Until health board service plans have been received in the Department of Health and Children, it will not be possible to indicate the amount of money allocated for RAPID in 2003.
Clár Funded Health Projects

Health Board

Total funding required for identified project

Total CLÁR funding

Western Health Board

975,115

204,486

Mid-Western Health Board

176,000

58,500

Midland Health Board

200,000

50,000

North-Western Health Board

813,500

270,833

Southern Health Board

448,696

123,217

Southern Health Board (Major Project)

805,000

226,000

Total

3,418,311

933,036

Clár Programme 2002-2003 Western Health Board.

District

Service

Type of Development

Total Cost

CLÁRFunding

Range of Islands Inisboffin, Clare Island, Inis Biggle.

Ambulance Programme – cardiac ambulance service being provided by trained volunteers acting as Emergency Medical First Responders on the Islands.

Ambulance Programme – The majority of the costs relate to the purchase of Defibrillator equipment for each of the Islands

38,115

12,705

Boyle, County Roscommon

Health Centre

Health CentreComplete furbishment of the centre i.e. – fixtures, fittings, furniture, equipment, chairs, desks, office equipment, blinds, carpets etc.

130,000

25,395

Elphin

Health Centre

Health CentreComplete furbishment of the centre i.e. – fixtures, fittings, furniture, equipment, chairs, desks, office equipment, blinds, carpets etc.

165,000

50,000

Achill

Health Centre

Health CentreComplete furbishment of the centre i.e. – fixtures, fittings, furniture, equipment, chairs, desks, office equipment, blinds, carpets etc.

260,000

12,697

Various Areas

A variety of small refurbishment projects in Health Centres, District Hospitals and the Ambulance Services for which co-funding exists.

Clifden Base Lodge – Wiring and electrical work, plumbing, new doors required.Belmullet District Hospital – Refurbishment of two four bedded wards

160,000140,000

50,00032,000

Kilkieran Health Centre – Refurbishment and re-equipping of accommodation for GP, Community Welfare Officer and visitors waiting area.

50,000

11,689

Killala Health CentreRefurbishment of access area to Centre

32,000

10,000

(€103,689)

Total

975,115

204,486

Clár Programme 2002-2003 Mid-Western Health Board

District

Service

Type of Development

Total Cost

CLÁRFunding

Ennistymon Community Hospital

Develop activation area at Ennistymon Community Hospital

Activation Area development.

76,000

25,500

Ennistymon Community Hospital

Upgrading of Hospital Entrance.

Upgrading of Hospital Entrance and Reception area, granting wheelchair access; upgrading Hospital entrance and providing new Hospital Reception to the new Palliative Care Beds currently being commissioned.

100,000

33,000

Total

176,000

58,500

CLAR Programme – 2002-2003 Midland Health Board

District

Service

Type of Development

Total Cost

CLÁRFunding

Aughnacliffe, County Longford

Health Centre

Upgrade and Modernisation of Health Centre

200,000

50,000

Total

200,000

50,000

CLÁR Programme 2002-2003 North-Western Health Board

District

Service

Type of Development

Total Cost

Clár Funding

Counties Sligo, Leitrim and Donegal

Learning Disability Centres

People Carriers × 5 – to Serve the residents of 5 districts

150,000

50,000

1.Dungloe, County Donegal DED 33047

2.Dromahair, County Leitrim DED 28039

3.Tubbercurry, County Sligo DED 31082

4.Glenties, County Donegal DED 33052

5.Fanad, Doecastle, County Donegal DED33033

Glen, County Donegal

DED 33116

Termon, County Donegal DED 33116

Loughkeel, County Donegal DED 33122

County Donegal (Islands) DED 3304

Telemedicine Pilot Scheme

Objective is to put telemedicine service in place on a pilot basis.

82,000

27,333

Focused initially on Arranmore. Community Links Steering Group in place. To address service provision difficulties arising from population decline and lack of critical mass.

County Leitrim Location Manorhamilton D.E.D. ID 28052

Mental Health Services

Supervised Residential Unit Manorhamilton for 8-11 persons. To combine home and activity facilities. Refurbishment of old Manse, which is already in Board ownership. This work can proceed this year (2002).

150,000

50,000

District

Service

Type of Development

Total Cost

Clár Funding

St. Patrick's Hospital, Carrick-On-Shannon, County Leitrim

Residential and Day Unit for elderly.

Extensive rewiring including replacement of Distribution Boards, MCBs and RCDs and associated works. This work will be undertaken in 2002. Tender documents at preparation stage.

150,000

50,000

West Cavan DED 32088

Blacklion Health Centre

Complete Refurbishment and up-grading of existing H.C

60,000

20,000

Dungloe, County Donegal DED 33047

District Hospital and Primary Care Centre

Upgrading works at District Hospital and the Primary Care Centre to include: –

100,000

33,000

Building fabric improvements

Upgraded shower and WC areas.

External works including service roadway.

Kitchen upgrade and equipment to meet MASSOP Regulations

Various Locations Counties Donegal and Sligo.

Primary Care health centres and day centres. These works will ensure the continuation of vital services in mainly rural areas and full compliance with the EU (Hygiene and Foodstuffs) Regulations 2002)

Kitchen-Catering facilities upgrades and equipment to meet HACCP Requirements at various locations, viz:(A) Arranmore Island Health and Day Centre – DED ID 33040 County Donegal(B) Creeslough Day Centre – D.E.D ID 33031 County Donegal

27,00027,000

9,0009,000

(C) Glenties Day Centre - D.E.D ID 33052 County Donegal

27,000

9,000

(D) Riverstown Health-Day Centre D.E.D ID 31059 County Sligo

15,000

5,000

(E) Easky Health Centre County Sligo D.E.D ID 31024

9,000

3,000

(F) Tubbercurry Health Centre County Sligo D.E.D ID 31082

9,000

3,000

(G) Gurteen Health Centre County Sligo.

7,500

2,500

Sub Total

Sub Total

(€121,500)

(€40,500)

Total

813,500

270,833

Clár Programme 2002-2003 Southern Health Board

District

Service

Type of Development

Total Cost

Clár Funding

Sliabh Luachra

Day care centre at Ballydesmond

Creation of day care centre at Ballydesmond

50,000

16,500

Kerry, Various

Social Satellite Centres. Upgrades-refurbishment of social satellite centres

Murioch Upgrade laundry element and furnishingsVentry Upgrade furnishings and

5,0796,349

1,693 2,116

equipment

The Glen, Ballinskelligs Refurbishment and upgrading of kitchen

25,395

8,465

Glenflesk Upgrade Kitchen

6,349

2,116

Kenmare Refurbishment

12,697

4,232

Kells-Foilmore Equipment Furnishings

6,349

2,116

Waterville Upgrade Equipment and Furnishings

6,349

2,116

Sneem Upgrade Equipment and Furnishings

12,697

4,232

Templenoe Upgrade kitchen and dayroom

12,697

4,233

District

Service

Type of Development

Total Cost

Clár Funding

Kerry, Various – contd.

Dawros-Lauragh Improve Accessibility

12,697

4,233

Tuosist – Improve Accessibility

12,697

4,233

Dungegan, Ballinskelligs

Provision of equipment and furnishings for the centre and also some decoration and improvement work.

12,697

4,233

Mastergeehy Provision of furnishing and equipment

12,697

4,233

Valentia Replace kitchen equipment

12,697

4,233

Cordal Provision of new centre within existing community centre

12,697

4,233

W/Cork, Sherkin Island

Health Centre development, in conjunction with Sherkin Development society.

Develop Health Service Support to Island Communities. At West Cork it is proposed to

228,553

50,000

develop a Health Centre and Health clinic as part of a Community Resource centre on the Island.

Total

448,696