Thank you, Chairman. As this is my first appearance before the committee, I take the opportunity to welcome its establishment and I look forward to working with members from all sides of the House in making an input to transport issues. The remit of my Department is very substantial, encompassing roads, rail, aviation, road safety and related matters. I look forward to many discussions with the committee over the months and years ahead. My Department officials will be available at all times to attend meetings of the committee and discuss such matters as members may require. It is a matter for Members to decide the issues they wish to discuss.
With regard to the business in hand, the gross total of the Supplementary Estimate I am seeking is €126.1 million. This figure is offset by savings of €26.1 million on six subheads, leaving a net requirement of €100.056 million. There are three reasons for this Supplementary Estimate: the first is to cover major additional funding on roads maintenance and improvement: the second relates to adjustments regarding the national emergency plan; and the third element concerns fees for the legal action in relation to the Sellafield MOX plant, although this issue is no longer being dealt with by my Department.
The national development plan provides a clear strategy for the development of our national road network to the high standard necessary to support economic and social development and to facilitate regional development. The challenge now is to implement the strategy as urgently as possible. The Government has allocated considerable resources to the national roads programme, with investment of approximately €2.62 billion over the period 2000-02. There were 27 projects comprising 169 km of road, including nearly 50 km of motorway or dual carriageway standard, which have been completed to date and opened to traffic. Work is ongoing on a further 19 projects, comprising 154.5 km of road, including 121.5 km of motorway/dual carriageway standard. Of these, 12 are expected to be completed and open to traffic between now and the end of 2003.
A further 22 projects involving 224 km of road have obtained the necessary statutory approvals and are working through the system. Planning and design work has been advanced on approximately 65 other major projects and preferred route corridors have been identified for the five main interurban routes, which have now been finally agreed. A large PPP programme of 11 projects has been developed, of which one is in construction and four are at an advanced tender stage.
There has also been significant progress in 2002 on many major road schemes in the national development plan, including the Dublin Port tunnel, which is a major scheme involving very substantial investment; the M50 south eastern motorway, a key investment for the State; and the Kildare, Glen of the Downs and Ballincollig bypasses. We have made very substantial progress on all of those projects within the past 12 months. Projects completed in 2002 include the Enfield relief road, N18 Newmarket-on-Fergus bypass, which was officially opened recently, the N22 between Bealagrellagh and Gortatlea and the N25 from Rathsillagh to Harristown.
This substantial level of activity on roads projects has resulted in higher than anticipated levels of expenditure, which has necessitated a Supplementary Estimate of €125 million in respect of grant payments to the National Roads Authority. The bulk of the additional expenditure arises on schemes in progress or completed and PPP schemes at tender stage. Other factors that have given rise to additional expenditure include greater than anticipated progress on construction on the M 1 Cloghran-Lissenhall and Lissenhall-Balbriggan sections and the Drogheda, Watergrasshill, and N25 Youghal bypasses. Other factors include a price variation clause and risk buy-out on the Kildare bypass, land purchase liabilities maturing earlier than anticipated on schemes such as the Kilcock-Kinnegad motorway, the Monasterevin bypass and the Navan Road interchanges, and increased land acquisition costs generally.
Costs have increased significantly in recent years for a variety of reasons, including construction cost inflation, which was estimated at 15% per annum in 1999 and 2000 and 9.5% in 2001. I am pleased that this inflation has moderated, with a figure of 5% projected for 2002. The moderation in construction inflation will lead to the NRA being able to obtain better prices and to insist on tighter schemes.
The increase in the cost of the programme and changed economic and budgetary circumstances, combined with some delays, due partly to land access difficulties in 2001 affecting planning, have impacted on the pace of the programme. Some projects will, therefore, take longer to implement than planned. However, it is hoped that, with many projects reaching completion in 2003 and the advance of PPP projects, a number of schemes will be able to commence next year.
I will now deal with the administrative provisions of the Supplementary Estimate. A total of €1.156 million is being provided under the administrative subheads: €4,000 is being provided under subhead A3, advertising of the national emergency plan; €490,000 in respect of subhead A4, the postage costs of the plan; and a sum of €662,000 is provided under subhead A7, which relates to consultancy services. The latter subhead consists of €279,000 for national emergency plan design fees and €383,000 for fees arising from the Sellafield MOX plan legal action. Under the departmental restructuring that took place in June, these matters are now the responsibility of the Minister for the Environment and Local Government. The moneys relate to expenditure incurred by the former Department of Public Enterprise up to 18 June, which are being accounted for in the Department of Transport Vote for 2002. Moneys spent after 18 June in respect of these items will be accounted for in the Vote of the Department of Environment and Local Government.
I have outlined most of the reasons that I need an additional €100.056 million in this Supplementary Estimate. The committee is also being asked to consider savings that have been made in relation to transport matters such as Luas, the public transport investment programme, the CIE railway development programme, regional airports and the DTO. Most of these savings, which come to a total of approximately €26 million, arise as a result of unforeseen timing circumstances. The committee is aware that capital moneys, including the funds under question, are only paid out when they are required. If a capital project does not meet its deadlines, the funds will not be paid put. The overall projected excess is some €126 million which, when offset by the savings of €26 million to which I referred, leaves a net requirement in this Estimate of about €100 million. I would be happy to answer any questions of the Chairman and the other members of the committee.