A Breakdown of the €9 million Capital Funding Spent in December 2012 by my Department and associated bodies is as follows:
Vote
|
ICT €000
|
Building & Equipment €000
|
Lab Equipment* €000
|
Vote Sub-Total €000
|
Justice
|
839
|
|
185
|
1,024
|
Garda
|
2,942
|
|
|
2,942
|
Prisons
|
573
|
2,337
|
|
2,910
|
Courts
|
1,940
|
377
|
|
2,317
|
PRA
|
11
|
|
|
11
|
Total
|
6,305
|
2,714
|
185
|
9,204
|
*Deferred Capital Expenditure in relation to Forensic Science Laboratory.
This is not an unusual occurrence as capital expenditure does not, by its nature, accrue evenly over the course of a year. It is generally related to project milestones and in particular, project completion. This can be particularly so with ICT capital expenditure, where contracts entered into at the beginning of a particular year are contracted for completion during the latter part of the same year, thus triggering final payments.