Central Bank of Ireland Expenditure

Dáil Éireann Debate, Thursday - 16 July 2015

Thursday, 16 July 2015

Questions (222)

Michael McGrath

Question:

222. Deputy Michael McGrath asked the Minister for Finance if he will provide an update on the Central Bank of Ireland moving its headquarters to the North Wall in Dublin 1; the costs incurred in the project to date; the date on which the move will be completed; and if he will make a statement on the matter. [30295/15]

View answer

Written answers

I am informed by the Central Bank that the total costs incurred on the project to 30 May 2015 amount to €17.8 million.

In terms of timelines, I am informed by the Central Bank that the current programme foresees completion of construction on site in the last quarter of 2016 with the commencement of occupation of staff thereafter.