Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Central Bank of Ireland Expenditure

Dáil Éireann Debate, Thursday - 16 July 2015

Thursday, 16 July 2015

Ceisteanna (222)

Michael McGrath

Ceist:

222. Deputy Michael McGrath asked the Minister for Finance if he will provide an update on the Central Bank of Ireland moving its headquarters to the North Wall in Dublin 1; the costs incurred in the project to date; the date on which the move will be completed; and if he will make a statement on the matter. [30295/15]

Amharc ar fhreagra

Freagraí scríofa

I am informed by the Central Bank that the total costs incurred on the project to 30 May 2015 amount to €17.8 million.

In terms of timelines, I am informed by the Central Bank that the current programme foresees completion of construction on site in the last quarter of 2016 with the commencement of occupation of staff thereafter.

Barr
Roinn