Electricity Transmission Network

Dáil Éireann Debate, Wednesday - 9 November 2016

Wednesday, 9 November 2016

Questions (186)

Seán Fleming

Question:

186. Deputy Sean Fleming asked the Minister for Communications, Climate Action and Environment if he has been informed or given any indication of non-compliance with the strategic environmental assessment directive regarding the gate 3 decision by the Commission for Energy Regulation; and if he will make a statement on the matter. [34010/16]

View answer

Written answers

The regulation of the electricity network is a matter for the Commission for Energy Regulation (CER) which is an independent statutory body and I have no function in the matter.

The Gate process, including the Gate 3 process, is an administrative grid connection process managed by the CER in accordance with its regulatory functions. I am informed by the CER that a Strategic Environmental Assessment (SEA) was not required in regard to Gate 3 and therefore the issue of non-compliance does not arise. However, as is the case with all Directions issued by the  CER, the Gate 3 Direction was subject to public consultation before being finalised in December 2008.

Top
Share