Schools Building Projects Status

Dáil Éireann Debate, Thursday - 12 July 2018

Thursday, 12 July 2018

Questions (197)

Robert Troy

Question:

197. Deputy Robert Troy asked the Minister for Education and Skills the status of applications for works submitted by a school (details supplied). [32390/18]

View answer

Written answers

Both schools to which the Deputy refers are included in my Departments 6 year construction programme and are scheduled therein to go to construction in 2019-2021. The schools' building projects are currently at tender stage.  Tenders were invited on 31 May 2018 and the tender return date is 16 August 2018.  The appointment of a contractor following the tender competition is expected in Quarter 4 of 2018.