Skip to main content
Normal View

Hazardous Waste Removal

Dáil Éireann Debate, Tuesday - 5 February 2019

Tuesday, 5 February 2019

Questions (487)

Micheál Martin

Question:

487. Deputy Micheál Martin asked the Minister for Agriculture, Food and the Marine the status of the remediation work on Haulbowline Island; the completion date for the remediation works; and if he will make a statement on the matter. [5079/19]

View answer

Written answers

My Department assumed responsibility for remediation works at Haulbowline Island on behalf of the Irish Government in 2012 with a particular focus on bringing about compliance with the terms of a CJEU judgment (Case C-494/01) under the Waste Framework Directive concerning the East Tip site. Funding for the remediation project is currently provided to my Department, in accordance with the specific conditions set out by the Minister for Public Expenditure and Reform, on an annual basis up to the completion date of the remediation works.

The East Tip works are the most significant element of the remediation project. In the period up to 2017 expenditure was focussed on preparing for and securing the necessary planning and waste licence consents for the East Tip remediation and upgrading the island infrastructure in anticipation of works. Following the signing of contracts in July 2017, the remediation of the East Tip commenced and in December 2018 I visited the site to see that the works had been substantially completed. I understand that there are some minor finishing works on the site to be completed early this year and the access road leading into the site is also being upgraded.

While the priority has been remediation of the East Tip, work on assessing a suitable solution for the former steelworks factory site has also been advanced in preparation for the next phase of the remediation project. Detailed site investigations have been undertaken and the preparation of an application for planning consent has also been advanced. The Government has decided that the Minister for Defence will be the ultimate owner of Haulbowline Island, in keeping with the main occupancy of the island, being the headquarters for the Irish Naval Service. Any remediation solution for these areas will need to be cognisant of their likely long term use. The Department of Defence has advised that it has engaged specialist engineers to examine the areas in question in order to explore the potential of these areas for naval operations in the future which will inform and direct remediation works in the first instance. Information from site investigation studies and assessments to date has been made available to the Department of Defence to assist in this work.

Top
Share