Howth Fishery Harbour Centre is one of the six designated Fishery Harbour Centres which are owned, managed and maintained by my Department under Statute.
Capital funding is made available on an annual basis by my Department to the Fishery Harbour Centres, via the Fishery Harbour and Coastal Infrastructure Development Programme.
In May, I announced a capital investment package of €38.3million in the 2021 Fishery Harbour and Coastal Infrastructure Development Programme, and of that €8.295million has been allocated to works at Howth Fishery Harbour Centre. Details of the funding allocated to Howth FHC under the Fishery Harbour & Coastal Infrastructure Development Programme 2021 are in the attached table. These capital works are fully funded by my Department. Since 2010, €14.68million has been invested in Howth FHC.
Funding Allocated to Howth Fishery Harbour Centre under the Fishery Harbour & Coastal Infrastructure Development Programme 2021
|
Project Description
|
Cost €m
|
Middle Pier Berthing Face
Harbour Workshop
HM & Engineering Office
Harbour Dredging
Other Contractual Commitments
CCTV Upgrade
Fishermans’ toilet & shower facility
No 11 West Pier Building Upgrade
Boat store upgrade
Safety and Maintenance
Disability Access
|
6.00
0.90
0.05
0.20
0.30
0.075
0.15
0.25
0.05
0.30
0.02
|
Total
|
8.295
|