Dáil Éireann Debate, Tuesday - 20 September 2022

Tuesday, 20 September 2022

Questions (332)

Denis Naughten

Question:

332. Deputy Denis Naughten asked the Minister for Education the number of new school buildings that have been constructed since 2020; the type of heating system provided in each school constructed in tabular form; if a solar panel was installed in each instance; and if she will make a statement on the matter. [45660/22]

View answer

Written answers

Under Project Ireland 2040, the education sector will receive a total of approximately €4.4 billion capital investment over the period 2021-2025. This significant investment allows us to move forward with certainty on our ambitious plans and deliver high quality building projects, with a real focus on sustainability, for school communities across Ireland. This investment will build on the good progress being made on adding capacity to cater for demographic changes and provision for children with special educational needs. This investment will also facilitate an increased focus on the modernisation of existing school stock and help transition the school system for an era of net zero carbon by 2050.

My Department has a large pipeline of projects for delivery under the school building programme. The main elements of this pipeline currently involve in excess of 1,300 school building projects for delivery under the Department’s Large Scale and Additional Accommodation Scheme. These projects are currently in progress across the various stages of planning, design, tender and construction. Most of which are expected to be either under construction or completed in the period up to 2025.

A list of all capital projects completed under the Large Scale and Additional Accommodation Scheme, in county order, from 2010 to date may be viewed my Department’s website at www.education.ie .   This is updated on a monthly basis to reflect their progress through the various stages of capital appraisal, site acquisition, design, tender and construction.

My Department is at the forefront of design with respect to sustainable energy in school buildings and this performance has been recognised at both National and International level with sustainable energy awards for excellence in Design and Specification.

New renewable technologies and approaches are tested to ensure compatibility with school design and operational requirements under the research programme.  Successful and repeatable results are then incorporated into all new school designs and refurbishments through my Department’s Technical Guidance Documents, which set the benchmark for sustainable design in school buildings with a clear focus on energy efficiency. The Department’s policy is supported by a strong research programme with fifty three research projects at various stages including the energy website www.energyineducation.ie . which is a joint partnership with the Sustainable Energy Authority of Ireland (SEAI).                          

Schools designed and built in accordance with the Department’s schools technical guidance documents have been achieving A3 Building Energy Ratings since 2009 with schools typically achieving up to 20% higher performance and 25% better carbon performance than required by the 2019 Building Regulations,  along with 10% of primary energy provided via photovoltaics and infrastructure provision for electric vehicle charging.

The Department have been using test schools to evaluate the suitability of renewable energy options for schools over the past twenty plus years. Nearly 60 % of the research programme features renewable aspects. These renewables include wind generation, solar hot water heating, photovoltaics, rain water recovery, geothermal heat pumps, air source heat pumps and biomass heating systems. Results have varied with respect to their applicability in a school environment.  Research continues in many areas.

My Department and the Department of Environment, Climate and Communications established a jointly funded pathfinder programme with the SEAI, testing and demonstrating energy efficiency and decarbonisation retrofit approaches. This pathfinder is a great example of collaboration ensuring the deployment of new design approaches and technologies are introduced to the educational environment on an evidence based approach.

This Pathfinder programme is paving the way for, and informing, a much larger national schools’ programme for the energy retrofit of schools built prior to 2008 as included in the National Development Plan. It is facilitating research on a range of typical retrofit options, which will have been tried and tested. It is providing valuable development information for a solution driven delivery strategy which will be founded on a solid evidence base that has proven the robustness and scalability of renewable solutions within the schools’ sector. 

The longer-term outcome of the pathfinder will be to create an accurate and scalable model for energy efficient retrofits of schools across Ireland.

The pathfinder programme builds on significant investment by the Department of Education in energy efficiency through the 2009/10 Cavity and Attic Insulation/Water Conservation Scheme and ongoing Summer Works and refurbishment projects.

The upgrades target a Building Energy Rating of B, 50% energy efficiency improvement and 51% emissions reduction. The works typically involves upgrades to the building fabric including wall and roof insulation, doors and windows, air tightness improvements, LED lighting and heating upgrades as well as renewable technologies.

The Department’s current approach to heating systems provides for direct modulating high efficiency gas boiler systems. This approach takes into account future proofing to ensure school buildings are renewable compatible and are able to take advantage of developing technologies as they become viable, thus enabling a Just Transition for school management, teachers, pupils and parents.

The Climate Action Plan 2021 Annex of Actions published earlier this year actions the Department to confirm its decarbonisation pathway trajectory to meet 2030 and 2050 targets for the schools sector by end of 2022.

Work is ongoing on decarbonisation options for schools with a focus on the standard of required design criteria and specification to achieve a net zero energy school building and establishing the trajectory for the integration of suitable solutions on a phased basis in a risk controlled manner providing a credible cost effective transition to zero carbon school buildings while ensuring no delays to school accommodation delivery.

The attached list shows the list of New School Buildings Completed since 2020.

List of New School Buildings completed 2020 to date

County

Roll No.

School

School Type

Year

Building Type

Cavan

19439B

Holy Family Ss, Cootehill

Primary

2021

New School Building

Cork

19993E

Gaelscoil An Ghort Alainn, Aibinne Murmont, Gort Alainn

Primary

2020

New School Building

Cork

19881Q

Gaelscoil Charraig Uí Leighin

Primary

2021

New School Building

Cork

20162O

Sonas Special Junior School

Primary

2021

New School Building

Cork

76273O

Gaelcholáiste Charrraig Uí Leighin

Post Primary

2021

New School Building

Cork

14052V

Kanturk BNS & SN an Chlochair, Kanturk.

Primary

2022

New School Building

Cork

17087J

S N AN CHLOCHAIR

Primary

2022

New School Building

Donegal

19927O

Scoil Mhuire B & C, Stranorlar

Primary

2022

New School Building

Dublin

19032R

Stewarts Hospital Special School, Palmerstown, D20

Primary

2020

New School Building

Dublin

20486R

Gracepark Etns, (All Hallows), D9

Primary

2020

New School Building

Dublin

76475D

Swords Community College

Post Primary

2020

New School Building

Dublin

17914S

St Oliver Plunkett, Malahide

Primary

2021

New School Building

Dublin

76213T

Lusk Community College - Phase Ii

Post Primary

2021

New School Building

Dublin

19727G

St Mary's Donnybrook

Primary

2022

New School Building

Dublin

20400E

Ballinteer ET, D16

Primary

2022

New School Building

Dublin

68308L

Malahide & Portmarnock ETSS

Post Primary

2022

New School Building

Galway

71270G

Clarin College (Gairmscoil Mhuire), Athenry

Post Primary

2020

New School Building

Galway

20330J

St Oliver'S Special School, Tuam

Primary

2021

New School Building

Kildare

70700A

Maynooth Post Primary School

Post Primary

2020

New School Building

Kildare

76193Q

Maynooth Community College

Post Primary

2020

New School Building

Kildare

16706G

St Joseph'S Ns, Kilcock

Primary

2021

New School Building

Kildare

20292E

Maynooth Etns

Primary

2021

New School Building

Kildare

76194S

Naas Community College

Primary

2022

New School Building

Laois

19337Q

St. Francis Special School, Portlaoise

Primary

2021

New School Building

Limerick

71840V

Coláiste Chiaráin, Croom

Post Primary

2020

New School Building

Meath

19671F

St Paul'S Ns, Abbeylands, Navan

Primary

2021

New School Building

Roscommon

68325L

Colaiste Chiarain, Summerhill Athlone

Post Primary

2020

New School Building

Westmeath

17327D

Curraghmore Ns

Primary

2020

New School Building

Wexford

19240B

St Patrick'S Special School, Enniscorthy

Primary

2021

New School Building

Wicklow

20045K

Gaelscoil Chill Mhantain, An Casadh Meidhreach, Ráth Naoi

Primary

2020

New School Building

Wicklow

20473I

Community National School Greystones

Primary

2021

New School Building