Dáil Éireann Debate, Tuesday - 8 November 2022

Tuesday, 8 November 2022

Questions (472)

Duncan Smith

Question:

472. Deputy Duncan Smith asked the Minister for Defence the amount of funding and investment provided for and spent in the Curragh training camp in County Kildare in each of the past three years; and if he will make a statement on the matter. [54247/22]

View answer

Written answers

I am assuming that the Deputy's question relates to major capital building investment at the DFTC, Curragh Camp for the past three years, 2019-2021 inclusive. The table below sets out the information sought.

2019

2020

2021

Refurbishment of Block 7 Plunkett

Refurbishment of Block 7 Plunkett

Refurbishment of Block 7 Plunkett

Ammunition Depot Building

Ammunition Depot Building

Ammunition Depot Building

Upgrade of Shower Rooms 1, 2 & 3, Cadet’s Mess

Upgrade of Shower Rooms 1, 2 & 3, Cadet’s Mess

Provision of Rifle Range & Associated Works

Provision of Rifle Range & Associated Works

CCTV Installation Upgrade

Pearse Barracks Refurbishment

Refurb Of Hospital Wards 2 And 8

Re-Roofing Of Disaster Store

Fire Proofing Upgrade, Cadet’s Mess

CCTV Installation Upgrade

Refurbishment of Hospital Wards 2 And 8

€2.955m

€2.587m

€2.143m

The Deputy may also wish to note the following major capital projects in respect of the DFTC which are included in the 5 Year infrastructure development programme and are either on site already or at an advanced stage of design delivery:

- Provision of a new Cadet school- main works are now underway and expected to be completed in 2023;

- Provision of a new CIS workshop- design team planning stage;

- Provision of a new ARW Headquarters- design team planning stage;