Housing Provision

Dáil Éireann Debate, Wednesday - 20 September 2023

Wednesday, 20 September 2023

Questions (538, 539, 540, 541, 542, 543, 544, 545, 546, 547, 548, 549, 550, 551, 552, 553, 554, 555, 556, 557, 558, 559, 560, 561, 562, 563, 564, 565, 566, 567, 568, 569, 570, 571, 572, 573, 574, 575, 579, 580, 581, 582, 583, 584, 585, 586, 587, 588, 589, 590, 591, 592, 593, 594, 595, 596, 597, 598, 599)

Duncan Smith

Question:

538. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 24 local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40481/23]

View answer

Duncan Smith

Question:

539. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 14 local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40482/23]

View answer

Duncan Smith

Question:

540. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the ten local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40483/23]

View answer

Duncan Smith

Question:

541. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the eight local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40484/23]

View answer

Duncan Smith

Question:

542. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the six AHB housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40485/23]

View answer

Duncan Smith

Question:

543. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the four local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40486/23]

View answer

Duncan Smith

Question:

544. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the two local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40487/23]

View answer

Duncan Smith

Question:

545. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the four local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40488/23]

View answer

Duncan Smith

Question:

546. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 30 local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40489/23]

View answer

Duncan Smith

Question:

547. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 30 local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40490/23]

View answer

Duncan Smith

Question:

548. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 21 local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40491/23]

View answer

Duncan Smith

Question:

549. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 18 local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40492/23]

View answer

Duncan Smith

Question:

550. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 17 local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40493/23]

View answer

Duncan Smith

Question:

551. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 16 AHB housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40494/23]

View answer

Duncan Smith

Question:

552. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the six AHB housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40495/23]

View answer

Duncan Smith

Question:

553. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the four AHB housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40496/23]

View answer

Duncan Smith

Question:

554. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the ten AHB housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40497/23]

View answer

Duncan Smith

Question:

555. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the eight AHB housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40498/23]

View answer

Duncan Smith

Question:

556. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the four AHB housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40499/23]

View answer

Duncan Smith

Question:

557. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the ten AHB housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40500/23]

View answer

Duncan Smith

Question:

558. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 32 local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40501/23]

View answer

Duncan Smith

Question:

559. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the eight local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40502/23]

View answer

Duncan Smith

Question:

560. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 20 local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40503/23]

View answer

Duncan Smith

Question:

561. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the eight local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40504/23]

View answer

Duncan Smith

Question:

562. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the six local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40505/23]

View answer

Duncan Smith

Question:

563. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the four local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40506/23]

View answer

Duncan Smith

Question:

564. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the four local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40507/23]

View answer

Duncan Smith

Question:

565. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the two local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40508/23]

View answer

Duncan Smith

Question:

566. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the two local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40509/23]

View answer

Duncan Smith

Question:

567. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 39 local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40510/23]

View answer

Duncan Smith

Question:

568. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 30 local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40511/23]

View answer

Duncan Smith

Question:

569. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 14 local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40512/23]

View answer

Duncan Smith

Question:

570. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 42 local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40513/23]

View answer

Duncan Smith

Question:

571. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 30 local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40514/23]

View answer

Duncan Smith

Question:

572. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 20 local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40515/23]

View answer

Duncan Smith

Question:

573. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 48 local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40516/23]

View answer

Duncan Smith

Question:

574. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 45 local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40517/23]

View answer

Duncan Smith

Question:

575. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the nine AHB units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40518/23]

View answer

Duncan Smith

Question:

579. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the five AHB units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40522/23]

View answer

Duncan Smith

Question:

580. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the purchase by local authorities of 28 turnkey housing units in a location (details supplied) was proceeded with; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40523/23]

View answer

Duncan Smith

Question:

581. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the purchase by local authorities of 61 turnkey housing units in a location (details supplied) was proceeded with; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40524/23]

View answer

Duncan Smith

Question:

582. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the purchase by local authorities of 26 turnkey housing units in a location (details supplied) was proceeded with; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40525/23]

View answer

Duncan Smith

Question:

583. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the purchase by local authorities of 34 turnkey housing units in a location (details supplied) was proceeded with; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40526/23]

View answer

Duncan Smith

Question:

584. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 19 AHB units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40527/23]

View answer

Duncan Smith

Question:

585. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 12 local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40528/23]

View answer

Duncan Smith

Question:

586. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 12 local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40529/23]

View answer

Duncan Smith

Question:

587. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 12 single rural local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40530/23]

View answer

Duncan Smith

Question:

588. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the four local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40531/23]

View answer

Duncan Smith

Question:

589. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the eight local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40532/23]

View answer

Duncan Smith

Question:

590. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the nine local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40533/23]

View answer

Duncan Smith

Question:

591. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the ten local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40534/23]

View answer

Duncan Smith

Question:

592. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the ten local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40535/23]

View answer

Duncan Smith

Question:

593. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the four local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40536/23]

View answer

Duncan Smith

Question:

594. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 22 local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40537/23]

View answer

Duncan Smith

Question:

595. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the 20 local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40538/23]

View answer

Duncan Smith

Question:

596. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the eight local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40539/23]

View answer

Duncan Smith

Question:

597. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the six AHB units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40540/23]

View answer

Duncan Smith

Question:

598. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the two local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40541/23]

View answer

Duncan Smith

Question:

599. Deputy Duncan Smith asked the Minister for Housing, Local Government and Heritage if the eight local authority housing units approved for construction in a location (details supplied) have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [40542/23]

View answer

Written answers

I propose to take Questions Nos. 538, 539, 540, 541, 542, 543, 544, 545, 546, 547, 548, 549, 550, 551, 552, 553, 554, 555, 556, 557, 558, 559, 560, 561, 562, 563, 564, 565, 566, 567, 568, 569, 570, 571, 572, 573, 574, 575, 579, 580, 581, 582, 583, 584, 585, 586, 587, 588, 589, 590, 591, 592, 593, 594, 595, 596, 597, 598 and 599 together.

The relevant details are being compiled and will be provided to the Deputy in accordance with Standing Orders.

The following deferred reply was received under Standing Order 51.
Please see below details as requested of each project.

Details Supplied

Current status of project

Dail Ref

40481/23 Bagenalstown, County Carlow in May 2015

24 new social homes completed Q3 2017 at a cost of €3.3m. Opened by Minister Eoghan Murphy in August 2017.

538

40482/23 Tullow, County Carlow in May 2015

16 new social homes completed Q4 2018 at a cost of €2m. Not opened by a Minister.

539

40483/23, Rathvilly, County Carlow in May 2015

10 new social homes completed Q2 2017 at a cost of €1.5m. Opened by Minister Damien English in May 2017.

540

40484/23 Myhill and Mount Leinster, County Carlow in May 2015

Myshall - 4 new social homes completed Q1 2018 at a cost of €641,935. Not opened by a Minister. Mount Leinster - 4 new social homes completed Q4 2017 at a cost of €550,027. Not opened by a Minister.

541

40485/23 Bagenalstown, County Carlow in July 2015

24 new social homes completed Q3 2017 at a cost was €3.3m. Opened by Minister Eoghan Murphy in August 2017.

542

40486/23 Borris, County Carlow in May 2015

4 new social homes completed Q3 2017 at a cost of €507,244. Not opened by a Minister.

543

40487/23 Rathvilly and Tullow, County Carlow in May 2015

1 new social home completed Q3 2017 at a cost of €140,000. Not opened by a Minister.

544

40488/23 Hacketstown, County Carlow in January 2016

4 new social homes completed Q4 2018 at a cost of €741,298. Not opened by a Minister.

545

40489/23 Vicar Street, County Kilkenny in May 2015

This 30 unit project as originally approved did not progress due to flooding concerns on the site.

546

40490/23 Bolton, Callan, County Kilkenny in May 2015

38 new social homes completed Q3 2020 at a cost of €7.1m. Not opened by a Minister.

547

40491/23 The Butts, County Kilkenny in May 2015

The appropriate re-zoning of this site was not achieved which meant the original social housing project could not advance. The council is looking at options for further development of new housing in this area.

548

40492/23 Donaguile, Castlecomer, County Kilkenny in May 2015

33 new social homes completed Q2 2021 at a cost of €8.37m. I opened this project in September 2021

549

40493/23 Robertshill, County Kilkenny in May 2015

The advancement of housing at this site has not been possible due to secondary flooding issues.

550

40494/23 Prologue/Westcourt/Moate, Callan, County Kilkenny in July 2015

The AHB originally planned to develop 16 new special needs social homes at dispersed locations, however they were unable to advance the project at that scale and ultimately delivered 1 new social home at Garden Cottage, Callan completed in Q4 of 2017 at a cost of €0.13m. Not opened by a Minister.

551

40495/23 Greenshill, County Kilkenny in July 2015

This project did not proceed as the AHB was unable to complete the purchase of the site

552

40496/23 Ballytobin, Callan, County Kilkenny in July 2015

This project was withdrawn as the AHB involved was unable to advance it.

553

40497/23 Leamy Street, Waterford in July 2015

This project was delivered under the Repair and Leasing scheme completed in Q4 2018 at a cost of €400,000. Not opened by a Minister.

554

40498/23 Gleann Ealach, Dunhill, Waterford in July 2015

This project was withdrawn due to a refusal of planning permission.

555

40499/23 Powers Field, Hennessy's Road, Waterford in January 2016

The original project could not be advanced on a viable basis by the AHB and options for new social housing delivery on this site are being explored by WCCC.

556

40500/23 Wadding Manor, Ferrybank, Waterford in January 2016

10 new social homes completed Q2 2021 at a cost of €2.1 million. Not opened by a Minister.

557

40501/23 An Garran, Tramore, Waterford in January 2016

This 50 unit project project is currently on-site and scheduled for completion in Q4 2024. The current approved budget is €18.1 million.

558

40502/23 Ardmore Park - Priory Lawn, Waterford in May 2015

8 new social homes completed Q3 2020 at a cost of €1 million. Not opened by a Minister

559

40503/23 Ballinroad, Dungarvan, Waterford in May 2015

21 new social homes completed Q2 2020 at a cost of €4.6 million. Not opened by a Minister

560

40504/23 Coolfin Woods, Portlaw, Waterford in May 2015

12 new social homes completed Q2 2019 at a cost of €2.4 million. Not opened by a Minister

561

40505/23 Larchville, Waterford in May 2015

5 new social homes completed Q2 2021 at a cost of €1.4 million. Not opened by a Minister

562

40506/23 Tallow Alms House, Waterford in May 2015

4 new social homes completed Q4 2018 at a cost of €666,593. Not opened by a Minister

563

40507/23 Barrack St, Cappoquin, Waterford in May 2015

4 new social homes completed Q4 2017 at a cost of €875,633. Not opened by a Minister

564

40508/23 Patrick St., Waterford in May 2015

2 new social homes completed Q3 2018 at a cost of €562,192. Not opened by a Minister

565

40509/23 Cathal Brugha, Dungarvan, Waterford in May 2015

The project as proposed did not proceed and instead improvement works to the properties concerned were carried out under Retrofit Programmes.

566

40510/23 Kells, County Meath in May 2015

40 new social homes completed Q4 2020 at a cost of €9.98 million. I opened the project in April 2022.

567

40511/23 Athboy, County Meath in May 2015

32 new social homes completed Q2 2018 at a cost of €8.5 million. Opened by Minister Damien English in August 2018.

568

40512/23 Summerhill, County Meath in May 2015

19 new social homes completed Q4 2020 at a cost of €4.3 million. Not opened by a Minister.

569

40513/23 Kilbride Lane, Bray, County Wicklow in July 2015

42 new social homes completed, Phase 1 (23 homes) completed Q4 2020 and Phase 2 (19 homes) completed Q2 2021 at a cost of €17.34m. Not opened by a Minister

570

40514/23 Dunlavin (Phase 1), County Wicklow in May 2015

The project did not proceed due to flooding risks at the site

571

40515/23 Brewery Bends (Phase 2), Rathdrum, County Wicklow in May 2015

20 new social homes completed Q4 of 2018 at a cost of €4.57m. Opened by Minister Andrew Doyle in December 2018

572

40516/23 Kilnagleary, Carrigaline, County Cork in May 2015

49 new social homes completed, Phase 1 (10 units) and Phase 2 (5 Units) in Q4 2018, Phase 3 (16 Units) Q1 2019 and Phase 4 (18 Units) Q1 2019 at a cost of €12.5m. Not opened by a Minister.

573

40517/23 Beechgrove, Clonakilty, County Cork in May 2015

57 new social homes completed, Phase 1 (51 units) Q4 2021 and Phase 2 (6 units) Q2 2022 at a cost of €18.3m. Not opened by a Minister.

574

40518/23 Rosscarbery, County Cork in July 2015

9 new social homes completed Q1 2019 at a cost of €2.3m. Not opened by a Minister.

575

40522/23 Mount St. Joseph, Chapel Hill, Macroom, County Cork in July 2015

The project was withdrawn by the AHB as it was not economically viable. The needs to be supported by this project will be met through an alternative project, which is at pre-tender stage.

579

40523/23 Castletreasure, Donnybrook, Douglas, County Cork in January 2016

12 new social homes completed Q1 2017 at a cost of €2.8m. Opened by Minister Simon Coveney.

580

40524/23 Midleton, County Cork in January 2016

This project received approval as a Turnkey in 2016 but was subsequently withdrawn by the developer. The project was resubmitted as a 70 unit SHIP Construction project was approved in 2018. However, the project was put on hold in 2021 due to issues with NAMA and Irish Water.

581

40525/23 Passage West, County Cork in January 2016

This project was withdrawn by the Council due to An Bord Pleanala overturning the Council’s decision to grant permission for the development.

582

40526/23 Ballincollig, County Cork in January 2016

The project was withdrawn by the Council on 20 July 2017.

583

40527/23 Mitchels Road, Tralee, County Kerry in July 2015

18 new social homes are on site and due to complete shortly at an estimated cost of €4.7m.

584

40528/23 The Park, Killarney, County Kerry in May 2015

12 new social homes completed Q2 2018 at a cost of €2.1m. Opened by Minister Eoghan Murphy in July 2018.

585

40529/23 Killeen, County Kerry in May 2015

12 new social homes completed Q3 2019 at a cost of €2.2m. Not opened by a Minister.

586

40530/23 County Kerry in May 2015

9 new social homes completed between 2018 and 2022. Not opened by a Minister. 1 new social home currently onsite and due for completion Q2 2024. 2 other social homes are delayed due to legal issues.

587

40531/23 Lixnaw, County Kerry in May 2015

4 new social homes completed in Q4 2017 at a cost of €650,000. Not opened by a Minister.

588

40532/23 The Park, Killarney, County Kerry in January 2016

8 new social homes completed in Q2 2018 at a cost of €1.4m. Opened by Minister Eoghan Murphy in July 2018.

589

40533/23 Killeen, County Kerry in January 2016

9 new social homes completed in Q3 2019 at a cost of €1.6m. Not opened by a Minister.

590

40534/23 Listowel, County Kerry in January 2016

7 new social homes completed in Q4 2019 at a cost of €1.7m. Not opened by a Minister.

591

40535/23 Milltown, Bridewell, County Kerry in January 2016

8 new social homes completed in Q4 2019 at a cost of €2m. Not opened by a Minister.

592

40536/23 Bill Kinnerk Road, Tralee, County Kerry in January 2016

4 new social homes completed in Q1 2018 at a cost of €4.2m. Not opened by a Minister.

593

40537/23 Kenmare, County Kerry in January 2016

22 new social homes completed in Q4 2018 at a cost of €4.3m. Opened by Minister Eoghan Murphy in July 2019.

594

40538/23 Tubberhill, Westport, County Mayo in May 2015

21 new social homes (increased from 20) completed in Q1 2018 at a cost of €5.6m. Not opened by a Minister.

595

40539/23 County Mayo in July 2015

5 new social homes completed Q2 2017 and Q2 2018 at a cost of €1.1m. Not opened by a Minister.

596

40540/23 Knockferreen, Kilmaine Road, Ballinrobe, County Mayo in July 2015

6 new social homes completed in Q4 2018 at a cost of €0.9m. Not opened by a Minister.

597

40541/23 Marian Cresent, Ballina, County Mayo in May 2015

4 new social homes (increased from 3) completed in Q2 2018 at a cost of €0.8m. Opened by Minister Damian English in May 2018.

598

40542/23 Knockmore, Ballina, County Mayo in January 2016

8 new social homes completed in Q1 2019 at a cost of €2m. Opened by Minister Eoghan Murphy in March 2019.

599