Rural Schemes

Dáil Éireann Debate, Tuesday - 13 February 2024

Tuesday, 13 February 2024

Questions (628)

Thomas Pringle

Question:

628. Deputy Thomas Pringle asked the Minister for Rural and Community Development to outline, in tabular form, the amount of funding granted under the Rural Regeneration and Development Fund to projects in County Donegal, disaggregated by year funding was granted, title of project, amount of funding currently drawn down and estimated completion date; and if she will make a statement on the matter. [6437/24]

View answer

Written answers

The Rural Regeneration and Development Fund (RRDF) provides funding for the development and construction of capital projects in towns, villages and rural areas across Ireland.

To date, 215 projects have been approved for RRDF funding of €415 million for projects costing €571 million.

RRDF funding of €40.3 million has been allocated to 14 projects located in County Donegal. The table below lists the details of projects approved for funding in Donegal, as requested by the Deputy.

Year Funding Awarded

Project Title

Lead Party

Project Cost

RRDF Funding

Funding Drawn down to date

Estimated Completion Date

2018

GTeic Gaoth Dobhair

Údarás na Gaeltachta

€2,000,000

€1,498,961

€1,498,961

Project Completed

2018

Swan Park

Donegal County Council

€2,304,056

€1,724,495

€1,725,495

Project Completed

2019

Ocean Innovation Centre Ireland

Letterkenny Institute of Technology

€3,632,876.00

€2,724,657.00

€0

Q3 2024

2019

Killybegs 2040 - Town Centre Regeneration Project

Donegal County Council

€5,423,583

€4,067,687

€1,815,879

Q2 2025

2019

Ailt an Chorráin (Burtonport)/ Oileán Árainn Mhór (Arranmore Island) - Harbour to Island Regeneration

Donegal County Council

€4,118,932

€3,089,199

€2,050,951

Q2 2025

2019

DigiWest

Western Development Commission

€214,912

€161,183

€161,183

Project Completed

2020

Ballyshannon 2040 - Back to Ballyshannon

Donegal County Council

€247,500

€185,625

€116,980

Q3 2024

2020

Ramelton Historic Town Centre - A Restorative and Transformational Public Realm Scheme

Donegal County Council

€249,159

€186,869

€186,869

Q1 2024

2021

Ailt an Chorrain (Burtonport) Harbour Redevelopment Phase 2 Harbour Buildings

Donegal County Council

€2,295,290

€2,065,761

€87,603

Q3 2025

2021

Carndonagh TUS NUA Regeneration Project

Donegal County Council

€9,542,852.00

€8,218,982.00

€168,325.11

Q2 2025

2021

The Seed Project - Strenghten, Engage, Enable, Deliver

Donegal County Council

€9,756,969.00

€8,781,272.00

€253,770.60

Q4 2025

2022

Repowering Buncrana A NW Place Standard Project

Donegal County Council

€1,461,745

€1,169,396

€0

Q2 2025

2022

Cill Ulta: Northwest Bioeconomy Hub

Údarás na Gaeltachta

€245,149

€196,119

€24,000

Q2 2025

2022

Ramelton Re-Imagined

Donegal County Council

€7,949,898.00

€6,359,894.00

€0.00

Q1 2026