I can advise the Deputy that the following significant capital projects are currently underway at Casement Aerodrome and Haulbowline Naval Base, at stages ranging from design planning to construction, representing a total estimated value of over €47 million:
Project
|
Status
|
Casement Aerodrome
|
|
Casement Aerodrome: Military Medical Facility (Relocation of Bricins)
|
Currently undergoing planning and design
|
Casement Aerodrome: Main Technical Stores Refurbishment
|
Currently on site - expected completion in 2024
|
Casement Aerodrome: Hangar Upgrade and Doors
|
Currently on site - expected completion in 2024
|
Casement Aerodrome: Replacement Hangar
|
Currently undergoing planning and design
|
|
|
Haulbowline Naval Base
|
|
Haulbowline Naval Base: Upgrade of Block 4 Accommodation
|
Currently on site - expected completion 2025
|
Haulbowline Naval Base: Upgrade of Block 9 Office
|
Design Team appointed and currently undergoing planning and design
|
Haulbowline Naval Base: Refurbishment of Barracks Foreman Works Building
|
Contract signing imminent
|