Skip to main content
Normal View

The future of data centres in Ireland

Ireland’s growing data centre sector is a key challenge, pitting climate goals against growth of the digital economy. Amidst a global boom in digitalisation and artificial intelligence, Ireland has become a leading hub for data centres which are viewed as anchors for foreign direct investment. Aside banning them altogether, what policy avenues are ahead?

Ireland is a leading hub for data centres, attracting the likes of Microsoft, Meta, Google, and Amazon. Technology multinationals bring significant corporation tax takings, yet data centres are power-hungry and their growing energy needs pose a challenge for Ireland’s climate ambitions. Using carbon-free energy would be the optimum solution. However, Ireland’s progress on doubling its renewable electricity (RES-E) to 80% by 2030 is mismatched by the growing power demand faced today.

About the author

Kate Walsh is a Senior Parliamentary Researcher in the Library and Research Service, specialising in environmental science.

 

 library.and.research@oireachtas.ie

 

Data centres currently consume one fifth of Ireland’s electricity and are projected to use one-third in the next few years. This rise mostly relates to expansion by existing data centres, rather than new centres in the pipeline. Ireland’s current strategy (since 2021) is to essentially pause new electricity grid connections especially around Dublin pending a new decision on ‘large energy users’ by the Commission for Regulation of Utilities (CRU). Beyond a complete ban on new data centre sites in the future, there is a series of policy avenues ahead.

Green energy

Renewable electricity also described as green, clean, carbon-free and decarbonised all refer to broadly the same thing – electricity generated in a way that has minimal greenhouse gas emissions associated with it. About 40% of Ireland’s electricity was from renewables in 2023.

Electricity demand is outpacing generation

Electricity supply and grid stability are real concerns. Central to Ireland’s national climate action plan is energy decarbonisation via widespread electrification – of transport, homes, heating, and industry. In the Dublin area in particular, these sectors are all putting additional strain on the grid, but data centres are by far the most demanding. To date, the pace of renewable electricity development has lagged behind the rapid growth in data centre power consumption (see Figure 1).

Every year, EirGrid publishes a ten-year forecast for the electricity market of the island of Ireland. In 2024, it said 89% of the growth in total electricity needed in the next decade is attributed to data centres.

 

Ireland has around 121 data centres, operated by 24 providers.

Map of data centres and communications networks across Ireland and Dublin region

Data centres (orange symbols) are located close to the ESB Telecoms high-capacity fibre network (blue lines.) Of these, 16 data centre sites (grey symbols) are licensed by the Environmental Protection Agency for industrial emissions associated with on-site power generation capacity (as at November 2024.)

Development of data centres outside Dublin

Capacity constraints in the Dublin region are a key concern of the regulator, CRU. One strategy would be a plan-based approach, for new clusters of data centres in other regions that are close to coastal landing points for subsea power and communications interconnections. There is scope to develop infrastructure along existing road and rail conduits, making the likes of Cork, Limerick, and Waterford new candidate data centre hubs. Figure 2 shows maps of data centres and the existing high-capacity communications network.

Long-term strategic infrastructure development

Recently there have been a series of data centre planning application refusals, many citing energy concerns. Currently, all planning applications are made to local authorities. However, Section 49 of the Planning and Development (Amendment) Act 2018 adds large data centres (defined by land footprint not energy demands) to the list of strategic infrastructure development.

Once Section 49 is commenced, planning applications for any large data centre will be lodged directly with An Coimisiún Pleanála (formerly An Bord Pleanála.) A strategic national approach to planning any new data centres might serve to better balance competing energy, greenhouse gas emissions and digital infrastructure challenges.

Interim measures

Planned data centres must obtain a contract to connect to the grid before they are built. There is no moratorium on new data centres, but there are more hurdles than ever. The Dublin region grid is near maxed out in terms of its capacity. Since 2021, the CRU require that a data centre seeking a new connection to the electricity grid must provide on-site power generation or storage to match its power load needs. Industry and environmental campaigners are critical of this approach. In the short-term, bigger data centres are installing large generators on-site, making each an industrial greenhouse gas emitter.  Figure 2 displays data centres with an industrial emissions licence from the EPA.

Renewables and power purchase agreements (PPAs)

The 2024 Climate Action Plan sets ambitions to develop Irish renewable electricity sources in the next five years. Key 2030 targets are to:

  • build offshore wind generation capacity to 5 Gigawatts (GW) – enough to power over 3.5 million homes;
  • grow onshore wind power to 9 GW (from 4.5 GW today)
  • target solar power of 8 GW (currently 1.2 GW); and
  • secure 15% of renewable electricity via Power Purchase Agreements (PPAs).

Should the 2030 targets be reached, the planned generation capacity is enough to cover the anticipated growth in demand by data centres. Further, energy analysts argue that large electricity users including data centres would be necessary to balance the grid load.

What is a power purchase agreement?

PPAs are contractual arrangements between electricity generators and buyers – used to offset or account for energy use and enhance sustainability metrics. PPAs are not tracked at a national or EU level.

 

Today, many data centre operators are pursuing corporate PPAs to shore up their renewable energy needs, improve their sustainability credentials and underpin their social licence to operate. There is currently no requirement for data centres to adopt PPAs, yet there is pent up demand amongst larger operators with hard decarbonisation targets. It is anticipated that future energy supply from wind and solar farms would be ‘gobbled up’ by the sector as a result.

Going off-grid

Data centre operators complain that they cannot innovate their own energy solutions, as all electricity transmission is via a single national grid. In response to connection restrictions, new data centres plan to use natural gas which has a much worse carbon footprint than the grid electricity mix.

Legislating for private wire connections would free large energy users to connect directly to renewable sources such as wind and solar farms and bypass the national grid. Such connections could enable the establishment of energy parks, where data centres co-locate with renewable power sources and buy their power directly (via PPA). Some envisage islanded hubs of data centres that are independent of the grid altogether. However, such an approach would likely not meet the requirements of the top-tier data centre operators for power backup and data security. A national Private Wires Policy Framework is in development.

Energy Efficiency Directive and making use of waste heat

Under the recast Energy Efficiency Directive (EU/2023/1791) from May 2025 data centres will be required to report on their energy use and environmental impact annually.

 

The goal is greater transparency and comparable sustainability metrics. Ireland needs to transpose the Directive by October 2025.

Data centres provide an opportunity for recovery of low-grade heat. The Heat (Networks and Miscellaneous Provisions) Bill (not yet initiated) is expected to set out a framework for district heating and use of waste heat in communities. Such systems offer potential for low-cost and constant heat in residential and business sectors, that reduce overall greenhouse gas emissions.

Turning waste heat into a resource

Waste heat has potential for serving nearby businesses, homes and services via district heating schemes. Article 26 of the Energy Efficiency Directive requires even moderately sized data centres to utilise waste heat - unless they can demonstrate it is technically or economically unfeasible.

Data centres: where climate goals clash with economic growth

Future developments of the data centre sector will need to align with Ireland's climate objectives, focusing on decarbonising the energy supply. Data centres are considered vital to Ireland’s digital economy: they are anchors for numerous multinational ICT companies and their associated corporation and employment taxes. Whilst there are no specific figures published for data centre operating companies, it is noteworthy that Ireland is currently enjoying record incomes, with corporation tax nearly doubling since 2020 to €24 billion in 2023.

The policy options explored above are key and one risk of inaction is departure of new data centres business altogether. There are key decision crossroads now for the State to consider, including whether to:

  • Ban new data centres – at least while the State addresses the energy and grid infrastructure deficit
  • Restrict electricity grid access but exacerbate the carbon footprint of data centres that turn to natural gas in their own power generators
  • Accelerate build-out of electricity capacity, achieve the 2030 renewables goals, and promote new strategically located data centres around the country.
  • Legislate for measures that enhance and do not harm Ireland’s legally binding low-carbon targets, such as utilising waste heat, energy parks, PPAs and private renewable energy installations.

Data centres at a glance

The rise in electricity use by data centres is around 1 TWh per year – outpacing new renewable electricity sources Ireland has around 121 data centres operated by 24 providers Current estimates of between 2.5% and 4% of Irelands greenhouse gas emissions are attributed to data centres Data centres are termed ‘large energy users taxes income is linked to companies in the ICT sector including data centres – in 2023 thats around €4billion Energy consumption by data centres around the world is soaring due to AI 2015 2023 Data centres used 5% (1.2 TWh) of Irelands electricity Data centres used 21% (6.3 TWh) of Irelands electricity A increase in power demand in just 8 years The national target for renewable electricity from renewable energy sources ‘RES-E’ is 80% by 2030 In comparison, the 2024 share was 37% Future electricity generation plan is to have 9 GW of onshore wind , 5 GW of offshore wind and 8 GW of solar TARGET 80% by 2030 +1 TWh x 121

Research Matters

Research Matters - Key Issues for the 34th Dáil and 27th Seanad is a collection of articles about topics that Members will likely be grappling with over the coming years.

Compiled by expert researchers from the Parliamentary Research Service, each article identifies ways in which Members, as legislators and parliamentarians, can engage meaningfully with the issues outlined.

Print a copy of this article

Further reading

Get more insight with further suggested reading from the Parliamentary Research Service: Data centres and energy' (July, 2024). This Spotlight seeks to explore the scale of data centres in Ireland, including brand new data on their electricity consumption and forecasts for future demand.

Top
Share