Dáil Éireann debate -
Thursday, 14 May 1992

Vol. 419 No. 7

Written Answers. - Cork Schools.

Peter Barry

Question:

45 Mr. Barry asked the Minister for Education the number of schools in Cork city and county that are awaiting sanctions for building or extension; the length of the waiting period in each case; whether tenders were invited in each case; if so, when; and when work will commence in each case.

The information sought by the Deputy is set out in a tabular statement which I propose to circulate in the Official Report.

Post-Primary Building/Extension Projects in Cork City and County — 1992

The following is a list of major building/extension projects currently in planning in the post-primary sector:

Schools

Project

Planning Initiated

Present Position

Col an Phiarsaigh, Glanmaire

Additional Classrooms

1981

Detail Design/contract documents completed.

St. Patrick's Gardners Hill

6 classrooms

1990

Detail Design and contract documents examined.

Col. Choilm, Ballincollig

All-Irish Unit — 4 classrooms

1991

Detail design and contract documents completed.

Bishopstown CS

Hearing impaired Unit

1990

Developed sketch scheme and detail design being examined.

Kinsale CS

New School

1988

Developed sketch scheme and detail design being examined.

Note 1
The question of when tenders can be invited for a project is examined, at the stage when architectural planning has been completed, in the context of available resources and commitments on hand. At this stage it is not possible to indicate when construction will commence in the above cases.
Note 2 — Stages of Planning
Stage 1 — Site Report, etc.
Stage 2 — Outline Sketch Scheme
Stage 3 — Developed Sketch Scheme
Stage 4 — Detail Design
Stage 5 — Bill of Quantities/Contract documents
Stage 6 — Tender Stage
Primary Building Projects in Cork City and County — 1992
Tenders have been invited for the following building projects:—

Schools

Project

Planning Initiated

Present Position

Dromina

New School

Nov. 1989

Tenders received Sept. 1991.

Baltydaniel

New School

Dec. 1988

Tenders received 20/5/92

Minance Bridge

Extension

Nov. 1989

Tenders received 15/5/92.

The following primary building projects are at various stages of architectural planning.

Schools

Project

Planning Initiated

Present Position

Killavullen

Extension

Apr. 1990

Preparation of tender documents

Clontead

New

Aug. 1990

Sketch plans stage.

Ballycotton

Extension

Aug. 1990

Sketch plans stage.

Glenahulla

Extension

Oct. 1990

Sketch plans stage.

Coolea

New

Nov. 1990

Sketch plans stage.

Cloughdubh

New

Feb. 1990

Tender documents.

Kilbrittain

New

Feb. 1990

Tender documents.

Schull Convent

Extension

Oct. 1990

Sketch plans stage.

Tullylease

New

Nov. 1990

Sketch plans stage.

Cloghroe

Extension

Sep. 1990

Sketch plans stage.

Note 1 — Tenders Invited
When tenders have been received and examined, the question of the placing of contracts will arise for consideration in the context of the available capital resources. It is therefore not possible to say when construction work will commence.
Note 2 — Stages of Planning
The advancement of these projects through the different stages of planning is dependent on the available staffing and capital resources and my Department's other commitments on the primary schools building programme.