Written Answers. - Cork Schools.
Peter Barry
Question:
45
Mr. Barry
asked the
Minister for Education
the number of schools in Cork city and county that are awaiting sanctions for building or extension; the length of the waiting period in each case; whether tenders were invited in each case; if so, when; and when work will commence in each case.
The information sought by the Deputy is set out in a tabular statement which I propose to circulate in the Official Report.
Post-Primary Building/Extension Projects in Cork City and County — 1992
The following is a list of major building/extension projects currently in planning in the post-primary sector:
Schools
|
Project
|
Planning Initiated
|
Present Position
|
Col an Phiarsaigh, Glanmaire
|
Additional Classrooms
|
1981
|
Detail Design/contract documents completed.
|
St. Patrick's Gardners Hill
|
6 classrooms
|
1990
|
Detail Design and contract documents examined.
|
Col. Choilm, Ballincollig
|
All-Irish Unit — 4 classrooms
|
1991
|
Detail design and contract documents completed.
|
Bishopstown CS
|
Hearing impaired Unit
|
1990
|
Developed sketch scheme and detail design being examined.
|
Kinsale CS
|
New School
|
1988
|
Developed sketch scheme and detail design being examined.
|
Note 1
The question of when tenders can be invited for a project is examined, at the stage when architectural planning has been completed, in the context of available resources and commitments on hand. At this stage it is not possible to indicate when construction will commence in the above cases.
Note 2 — Stages of Planning
Stage 1 — Site Report, etc.
Stage 2 — Outline Sketch Scheme
Stage 3 — Developed Sketch Scheme
Stage 4 — Detail Design
Stage 5 — Bill of Quantities/Contract documents
Stage 6 — Tender Stage
Primary Building Projects in Cork City and County — 1992
Tenders have been invited for the following building projects:—
Schools
|
Project
|
Planning Initiated
|
Present Position
|
Dromina
|
New School
|
Nov. 1989
|
Tenders received Sept. 1991.
|
Baltydaniel
|
New School
|
Dec. 1988
|
Tenders received 20/5/92
|
Minance Bridge
|
Extension
|
Nov. 1989
|
Tenders received 15/5/92.
|
The following primary building projects are at various stages of architectural planning.
Schools
|
Project
|
Planning Initiated
|
Present Position
|
Killavullen
|
Extension
|
Apr. 1990
|
Preparation of tender documents
|
Clontead
|
New
|
Aug. 1990
|
Sketch plans stage.
|
Ballycotton
|
Extension
|
Aug. 1990
|
Sketch plans stage.
|
Glenahulla
|
Extension
|
Oct. 1990
|
Sketch plans stage.
|
Coolea
|
New
|
Nov. 1990
|
Sketch plans stage.
|
Cloughdubh
|
New
|
Feb. 1990
|
Tender documents.
|
Kilbrittain
|
New
|
Feb. 1990
|
Tender documents.
|
Schull Convent
|
Extension
|
Oct. 1990
|
Sketch plans stage.
|
Tullylease
|
New
|
Nov. 1990
|
Sketch plans stage.
|
Cloghroe
|
Extension
|
Sep. 1990
|
Sketch plans stage.
|
Note 1 — Tenders Invited
When tenders have been received and examined, the question of the placing of contracts will arise for consideration in the context of the available capital resources. It is therefore not possible to say when construction work will commence.
Note 2 — Stages of Planning
The advancement of these projects through the different stages of planning is dependent on the available staffing and capital resources and my Department's other commitments on the primary schools building programme.