Question:575 Mr. Deenihan asked the Minister for Education the present position regarding the provision of a 25 metre swimming pool with spectator facilities at Sligo.
Vol. 425 No. 7
575 Mr. Deenihan asked the Minister for Education the present position regarding the provision of a 25 metre swimming pool with spectator facilities at Sligo.
576 Mr. Deenihan asked the Minister for Education the present position regarding the provision of a new track, stand and other improvements at Santry Stadium in Dublin 11.
577 Mr. Deenihan asked the Minister for Education the present position regarding the provision of regional sport centres at Cork, Athlone and Galway.
I propose to take Questions Nos. 575, 576 and 577 together.
The information requested by the Deputy is in the form of a tabular statement which I propose to circulate in the Official Report.
Location |
Client |
Project |
Grant |
Present position |
£m. |
||||
Sligo |
Sligo Corporation |
25 metre swimming pool as an extension to the existing sports centre |
1.2 |
Construction work commenced in October 1992 and is due for completion in late 1993. |
Morton Stadium Santry, Dublin |
Dublin County Council |
Provision of a 1,200 seat grandstand, refurbishment of the track, upgrading of infield area and other general improvements |
1.3 |
Tenders for the track refurbishment are under consideration. Contract documents are virtually completed for the grandstand and the general works and it is expected that tenders will shortly be invited for this element of the project. |
Galway |
UCG |
Provision of a 400 metre synthetic athletic track & artificial pitch at University College Galway |
0.85 |
Work on the artificial pitch has been completed. It is anticipated that the athletic track will be completed by summer 1993 |
Galway Corporation |
Refurbishment and extension of the Leisureland swimming pool complex |
1 |
Construction work commenced in September, 1992 and is expected to be completed by summer 1993. |
|
Athlone |
Athlone |
Multi-purpose Sports Centre. |
1.5 |
Proposals submitted by a developer for the procurement of the project on the basis of a design, part-finance, construction and management package were withdrawn in June, 1992. Following the withdrawal of the development Athlone UDC have re-examined the sport and leisure requirements of the area and have made proposals to meet those needs. This report is under consideration by the Department at present and when a decision is reached in the matter planning for the project will continue. |
Cork |
Cork Corporation |
25 metre swimming pool with ancillary facilities |
1.75 |
Proposals for the procurement of this project on the basis of a design, construction, part-finance and management package are under consideration by my Department in consultation with Cork Corporation. |