As the Deputy is aware, Waterways Ireland is responsible for the day-to-day maintenance, operation and cleaning of the Grand Canal within the Dublin City Council area. In general, this comprises
the ongoing work of litter removal,
grass cutting and channel weed cutting in order to keep the channel open for navigation,
maintaining the towpaths in condition for walkers and other users, and
managing the flow of water through the locks to its discharge into the River Liffey.
Additionally in 2009, an extensive programme of maintenance works were completed which included:
Repairs to damaged lock gates at Ringsend and along the Circular Line;
Cobblestone surfacing, and cable and roadway repairs at the slipway at Ringsend; — Structural repairs to the Waterways Ireland Visitor Centre, as well as repairs to the boardwalk and area around the visitor centre, including new bollards;
Weed spraying in the channel along the entire length of the Circular Line;
Painting of all lock gates on the Circular Line;
Spot dredging at Charlemont Street, Baggot Street and Grand Canal Street;
Removal of dredged material and topsoil;
Levelling and bank repairs at Charlemont Street;
Installation of a new 3-phase electricity supply at Charlemont Place;
Jetty and bridge repairs along the Circular Line, including rebuilding of wing wall at Mount Street;
Completion of towpath re-surfacing along a 1.5km length from the 1st to the 3rd Lock on the Main Line, in conjunction with the Railway Procurement Authority;
Maintenance of trees along canal banks pre-March and post-August;
Commencement of a dredging contract for the Circular Line in early November 2009; and
An ongoing joint contract with local authorities to upgrade Inchicore to Lucan towpath to a shared cycle / pedestrian route.
Other planned works on the Grand Canal within the Dublin City Council area to be completed in 2009 include:
Provision of a new water tap at Charlemont Place;
Dredging of the Canal from Grand Canal Street to Baggot Street;
Continuation of the towpath contract from Inchicore to Lucan;
Commencement of a wall strengthening contract for the dock walls in Ringsend, Charlotte Quay;
Strengthening of the jetty deck system at Ocean Bar in Ringsend; and
Localised works to lock gates and bridges as identified.