Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Select Committee on Enterprise and Economic Strategy díospóireacht -
Tuesday, 12 Dec 1995

Energy (Miscellaneous Provisions) Bill, 1995: Committee Stage (Resumed).

NEW SECTION.
Debate resumed on amendment No. 3a:
In page 5, before section 3, to insert the following new section:
"3.—All third party access to all energy interconnectors will be the full responsibility of the national energy regulator who shall decide—
(a) volumes, pricing, and all other detail, etc.,
(b) that all appeals against decisions by the national energy regulator shall be made to the Minister for Transport, Energy and Communications, whose decisions shall be final in all matters.".
—(Deputy N. Treacy).

Amendment No. 3a was discussed with amendment No. 2. Is the amendment being withdrawn?

Amendment, by leave, withdrawn.
Barr
Roinn