Ceisteanna—Questions. Oral Answers. - New Bus Depot.

asked the Minister for Industry and Commerce if he will state (a) the estimated cost of the new bus depot at Store Street, Dublin, and (b) the approximate date when the work of construction will be completed.

I am informed by Córas Iompair Éireann that the original estimate of the cost of the building, made in 1946, was £450,000. In view of the substantial rise in costs since then the ultimate cost is expected to be considerably higher. It is expected that the work of construction will be completed by the middle of 1950.