Ceisteanna—Questions. Oral Answers. - Hand-won Peat-fired Stations.

Mr. Lemass

asked the Minister for Industry and Commerce if he will state the dates of commencement of the civil construction work at the sites of the proposed four hand-won, peat-fired stations, at Caherciveen, Miltown Malbay, Screeb and Gweedore, and the estimated dates for the completion of these stations.

The information sought by the Deputy is as follows:—

Station

Dates of commencement of civil construction work

Estimated dates of completion

Caherciveen

July, 1954

Summer, 1956

Miltown Malbay

May, 1954

Spring, 1956.

Screeb

June, 1954

Spring, 1956.

Gweedore

Expected January, 1955.

Autumn, 1956

The Electricity Supply Board states that the estimated dates for completion are subject to manufacturers delivering plant in time and availability of the necessary materials for construction.