andMr. Connolly asked the Minister for Transport and Power what is the present position in regard to the proposed extensions to Shannonbridge power station, County Offaly.

I am informed by the ESB that the civil engineering contract for the preliminary site work and the main boiler contract have been placed. The turbo-generator contract will be placed in the week ending 1st August, 1970. The expected date for completion of the Shannonbridge extension is 1974.