Ceisteanna—Questions. Oral Answers. - County Cork Rural Electrification.

1.

asked the Minister for Transport and Power when an electricity supply will be extended to the remainder of the Kealkil, Borlin, Coomhola, Dunmanway, Inchigeela, Clondrohid, and Carriganima areas of County Cork.

I am informed by the ESB that Carriganima and Clondrohid are in the board's Clondrohid rural area which is scheduled for recanvass under the rural electrification planned post-development scheme in early 1971. Construction work normally commences about six months after the canvass.

The remaining areas are not scheduled for recanvass before 1972.