Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Dáil Éireann díospóireacht -
Tuesday, 6 Mar 1990

Vol. 396 No. 6

Written Answers. - Tallaght (Dublin) Hospital Project.

Pat Rabbitte

Ceist:

180 Mr. Rabbitte asked the Minister for Health if he will give details of the timetable for commencement and completion of the planned Tallaght Hospital, Dublin 24; and whether he will ensure, in the arrangement of continuation contracts, that workers on site will include a reasonable proportion of local unemployed building workers.

The Tallaght hospital project is currently at an advanced stage of planning and it is expected that construction work will commence in 1991 and that commissioning will be completed by 1994.

Barr
Roinn