Officials from the planning and building unit of my Department visited Millstreet community school on 27 January 1999 and met with the school authorities and the design team. It was agreed that the design team would prepare a report with costings outlining the refurbishment works required at the school. This report was submitted to my Department on 19 February 1999 and is currently being evaluated by my Department's technical staff.
A meeting has been arranged for 23 February 1999 between officials from my Department, the school authorities and the design team in order to discuss this report and progress the project further.
With regard to the application for additional accommodation, the educational worksheet was forwarded from the school recently and the accommodation requirements of the school are currently being evaluated. A response will issue to the school authorities as soon as possible.