Project Actual Cost (if completed)
|
Estimated Cost-Current Status
|
Cuas a Dubhghlais Pier, Cape Clear Island, County Cork –€0.395 million.
|
Complete.
|
Kilronan Pier, Inishmore, County Galway –€21 million.
|
Preliminary Report complete.
|
Caladh Mór Pier, Inishmaan, County Galway –€10 million.
|
Approval given to prepare EIS and Planning and Foreshore Licence Applications.
|
Inisheer Pier, County Galway –€3 million.
|
Tenders being sought to prepare Preliminary Report.
|
Dredging of Inishboffin Harbour, County Galway –€1 million.
|
Preliminary Report complete. Works to commence and be completed in 2004.
|
Slipways at Ballycroy (mainland) and at Gob na Dubh on Inishbiggle, County Mayo €0.75 million.
|
To be completed by end 2003.
|
Clynish Pier, County Mayo –€0.236 million.
|
Complete
|
Clare Island and Inishturk Ferry Piers, County Mayo –€10.9 million.
|
Tenders for works contract currently being assessed.
|
Inishlyre Pier, County Mayo –€0.32 million.
|
To be completed by end 2003.
|
Inseghort Pier, County Mayo –€0.15million.
|
Preliminary Report complete.
|
Roonagh Pier, County Mayo (mainland pier serving Clare Island and Inishturk) –€1.94 million.
|
To be completed by end 2003.
|
Coney Island Pier, County Sligo –€0.15 million.
|
Preliminary Report complete.
|
Rannach Pier, Arranmore Island, County Donegal €1million.
|
Preliminary Report complete.
|
Magheraroarty Pier, County Donegal (mainland pier serving Tory and Inishboffin) –€2.125 million.
|
To be completed by end 2003.
|
Total €52.966 million
|
|