Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Consultancy Contracts.

Dáil Éireann Debate, Thursday - 13 October 2005

Thursday, 13 October 2005

Ceisteanna (115)

Bernard J. Durkan

Ceist:

114 Mr. Durkan asked the Minister for Arts, Sport and Tourism the cost of all consultancy work associated with the development at Campus Stadium Ireland; and if he will make a statement on the matter. [28550/05]

Amharc ar fhreagra

Freagraí scríofa

The only consultancy work commissioned by the Department in relation to the Campus Stadium Ireland project was in 2001. Consultants High Point Rendel were engaged by the Department to conduct an overview study of the costs of national stadium project. The cost of the consultancy contract was €391,338. Details of consultancy work commissioned by Campus and Stadium Ireland Development Ltd, CSID, would be a matter for the company.

Question No. 115 answered with QuestionNo. 19.
Barr
Roinn