123 Mr. Gregory asked the Minister for Finance when the Office of Public Works will complete the works to the river wall along East Wall Road, Dublin 3; the works involved; and if dredging of this section of the river will be considered. [15568/07]

Amharc ar fhreagra

Freagraí scríofa

The consultants undertaking the design of the works on the River Tolka have undertaken a new survey of river wall along East Wall Road. When their report has been received by Dublin City Council and the Office of Public Works further action will be considered.

As I have previously informed the Deputy, the River Tolka Flooding Study Report, from which all the works have been undertaken, did not contain any recommendations for dredging the channel in this area.