Schools Building Projects.

Dáil Éireann Debate, Tuesday - 10 February 2009

Tuesday, 10 February 2009

Ceisteanna (517, 518, 519, 520, 521, 522, 523, 524, 525)

Joe Carey

Ceist:

575 Deputy Joe Carey asked the Minister for Education and Science if he will give approval to a school (details supplied) to move their extension and refurbishment project to tender stage in his forthcoming announcements; and if he will make a statement on the matter. [4267/09]

Amharc ar fhreagra

Freagraí scríofa

The project to which the Deputy refers is at an advanced stage of architectural planning for an extension/refurbishment.

The progression of all large scale building projects, including this project, from initial design stage through to construction phase will be considered in the context of my Department's multi-annual School Building and Modernisation Programme. However, in light of current competing demands on the capital budget of the Department, it is not possible to give an indicative timeframe for the progression of the project at this time.

Joe Carey

Ceist:

576 Deputy Joe Carey asked the Minister for Education and Science if he will give approval to a school (details supplied) to move its development project to the next stage in his forthcoming announcements; and if he will make a statement on the matter. [4268/09]

Amharc ar fhreagra

It is my Department's intention to provide the school to which the Deputy refers with a new building on a greenfield site.

The progression of all large scale building projects, including this project, from initial design stage through to construction phase will be considered in the context of my Department's multi-annual School Building and Modernisation Programme. However, in light of current competing demands on the capital budget of the Department, it is not possible to give an indicative timeframe for the progression of the project at this time.

Joe Carey

Ceist:

577 Deputy Joe Carey asked the Minister for Education and Science if he will give approval to a school (details supplied) to move its project to the next stage in his forthcoming announcements; and if he will make a statement on the matter. [4269/09]

Amharc ar fhreagra

The school to which the Deputy refers has applied to my Department for an extension project.

The progression of all large scale building projects, including this project, from initial design stage through to construction phase will be considered in the context of my Department's multi-annual School Building and Modernisation Programme. However, in light of current competing demands on the capital budget of the Department, it is not possible to give an indicative timeframe for the progression of the project at this time.

Joe Carey

Ceist:

578 Deputy Joe Carey asked the Minister for Education and Science if he will give approval to a school (details supplied) to move its project to the next stage in his forthcoming announcements; and if he will make a statement on the matter. [4272/09]

Amharc ar fhreagra

The school to which the Deputy refers has applied to my Department for an extension project.

The progression of all large scale building projects, including this project, from initial design stage through to construction phase will be considered in the context of my Department's multi-annual School Building and Modernisation Programme. However, in light of current competing demands on the capital budget of the Department, it is not possible to give an indicative timeframe for the progression of the project at this time.

Joe Carey

Ceist:

579 Deputy Joe Carey asked the Minister for Education and Science if he will give approval to a school (details supplied) to move its extension and refurbishment project to the next stage in his forthcoming announcements; and if he will make a statement on the matter. [4273/09]

Amharc ar fhreagra

The building project for the school to which the Deputy refers is awaiting the appointment of a Design Team.

The progression of all large scale building projects, including this project, from initial design stage through to construction phase will be considered in the context of my Department's multi-annual School Building and Modernisation Programme. However, in light of current competing demands on the capital budget of the Department, it is not possible to give an indicative timeframe for the progression of the project at this time.

Joe Carey

Ceist:

580 Deputy Joe Carey asked the Minister for Education and Science if he will give approval to a school (details supplied) in County Clare to move its project to the next stage in his forthcoming announcements; and if he will make a statement on the matter. [4274/09]

Amharc ar fhreagra

The school to which the Deputy refers has applied for an extension/refurbishment project. The progression of all large scale building projects, including this project, from initial design stage through to construction phase will be considered in the context of my Department's multi-annual School Building and Modernisation Programme. However, in light of current competing demands on the capital budget of the Department, it is not possible to give an indicative timeframe for the progression of the project at this time.

Joe Carey

Ceist:

581 Deputy Joe Carey asked the Minister for Education and Science if he will give approval to a school (details supplied) in County Clare to move its extension and refurbishment project to the next stage in his forthcoming announcements; and if he will make a statement on the matter. [4277/09]

Amharc ar fhreagra

The school to which the Deputy refers has applied for an extension/refurbishment project. The progression of all large scale building projects, including this project, from initial design stage through to construction phase will be considered in the context of my Department's multi-annual School Building and Modernisation Programme. However, in light of current competing demands on the capital budget of the Department, it is not possible to give an indicative timeframe for the progression of the project at this time.

Joe Carey

Ceist:

582 Deputy Joe Carey asked the Minister for Education and Science if he will give approval to a school (details supplied) to move its extension and refurbishment project to the next stage in his forthcoming announcements; and if he will make a statement on the matter. [4278/09]

Amharc ar fhreagra

The school to which the Deputy refers has applied to my Department for an extension project. The progression of all large scale building projects, including this project, from initial design stage through to construction phase will be considered in the context of my Department's multi-annual School Building and Modernisation Programme. However, in light of current competing demands on the capital budget of the Department, it is not possible to give an indicative timeframe for the progression of the project at this time.

Joe Carey

Ceist:

583 Deputy Joe Carey asked the Minister for Education and Science if he will give approval to a school (details supplied) in County Clare to move their project to the next stage in his forthcoming announcements; and if he will make a statement on the matter. [4281/09]

Amharc ar fhreagra

It is the intention of my Department to provide the school to which he refers with a new building on a greenfield site.

The progression of all large scale building projects, including this project, from site acquisition and initial design stage through to the construction phase will be considered in the context of my Department's multi-annual School Building and Modernisation Programme. However, in light of current competing demands on the capital budget of the Department, it is not possible to give an indicative timeframe for the progression of the project at this time.

Barr