Schools Refurbishment.

Dáil Éireann Debate, Wednesday - 16 September 2009

Wednesday, 16 September 2009

Ceisteanna (1084)

John McGuinness

Ceist:

1235 Deputy John McGuinness asked the Minister for Education and Science if the contract cost and detail has been agreed for the school extension and refurbishment at a school (details supplied) in County Kilkenny; when the project will commence; the time frame involved; and if he will make a statement on the matter. [31016/09]

Amharc ar fhreagra

Freagraí scríofa

The project to which the Deputy refers is currently at Stage 2b (Detailed Design). The Design Team's Stage 2b submission has been examined by my Department and a number of issues have been raised. The Board of Management and Design Team have been requested to confirm in writing when all the issues have been addressed, and confirm full compliance. Upon receipt of the necessary confirmations, the project will be considered for progression to Tender Stage.