Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Prison Building Programme.

Dáil Éireann Debate, Wednesday - 7 October 2009

Wednesday, 7 October 2009

Ceisteanna (196)

Charles Flanagan

Ceist:

286 Deputy Charles Flanagan asked the Minister for Justice, Equality and Law Reform the amount of money expended on the Thornton Hall project to date; and if he will make a statement on the matter. [34728/09]

Amharc ar fhreagra

Freagraí scríofa

A total of €41.8m, the bulk of which relates to the cost of the site, which was largely offset by the sale of surplus prison lands at Shanganagh, County Dublin has been expended to end August 2009 on site acquisition costs, professional fees, site preparation and engineering surveys, landscaping and security work. As is the case with all major infrastructure projects a comprehensive set of geological, engineering and archaeological surveys were conducted at the site. These essential preliminary site surveys will help to reduce the overall construction programme once a contract is signed.

In June of this year the Government re-affirmed its commitment to developing a new prison campus at Thornton Hall, Kilsallaghan, County Dublin and approved the launching of a new tendering process for the construction of a more affordable and better value prison campus at Thornton. The aim is to provide good quality, regime focussed accommodation with appropriate support and rehabilitation facilities to prepare prisoners for re-integration back into society. The new facility will provide accommodation for 1,400 prisoners with operational flexibility to accommodate up to 2,200 prisoners in a range of security settings.

The development will now proceed on a phased basis with Phase one comprising essential basic preliminary works required for the development including the construction of the access route and perimeter wall. It is intended that this work will proceed in the short term on the basis of separate contracts. The tender documentation and scope of works are currently being drafted. It is anticipated that work on Phase one will commence towards the end of this year or early next year.

While Phase one work is in progress the procurement process for the buildings and other facilities that will make up the new prison campus will be examined and finalised in accordance with the Department of Finance guidelines for capital projects. The objective is to complete the design and procurement process for the main prison complex while the construction of the phase one work is underway. While an outline design plan has been prepared, work is ongoing on more detailed design plans which are required for the tendering process. The two phase approach means that once a contract is signed for Phase two -the main prison development — the fact that the preliminary works envisaged by Phase one will have already have been completed will allow for construction to commence immediately on the main prison buildings within a secured perimeter.

The development of the new prison campus at Thornton Hall is a complex project which is governed by Department of Finance and EU procurement guidelines. The guidelines set out a range of actions that must take place prior to inviting tenders for the project. The Irish Prison Service is being assisted in this work by the National Development Finance Agency. It is intended to invite tenders for the construction of the Phase 2 — the main prison development — next year. I would expect the new prison to be operational within 3 years of the signing of a contract for Phase 2.

Barr
Roinn