Ceisteanna (209, 210, 211, 212, 213, 214, 215, 216, 217, 218, 219, 220, 221, 222, 223, 224, 225, 226, 227, 228, 229, 230, 231, 232, 233, 234, 235, 236, 237, 238, 239, 240, 241, 242, 243, 244, 245, 246, 247, 248, 249)

Brian Hayes

Ceist:

209 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding expended on the summer works scheme in primary schools in 2009; the number of schools that received this funding; and if he will make a statement on the matter. [9812/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

210 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding expended on the provision of the minor works grant in primary school in 2009; and if he will make a statement on the matter. [9813/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

211 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget expended on the provision of emergency funding to primary schools in 2009; the number of schools that received this funding; and if he will make a statement on the matter. [9814/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

212 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget expended on the provision of prefabricated accommodation in primary schools in 2009; the number of schools that received this funding; and if he will make a statement on the matter. [9815/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

213 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget expended on the provision of school sites for primary schools in 2009; the number of schools expected to be built on these sites; and if he will make a statement on the matter. [9816/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

214 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget expended on architectural plans and design teams for primary school building projects in 2009; the number of school projects to which this funding applies; and if he will make a statement on the matter. [9817/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

215 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget expended on the construction of major capital projects in primary schools during the construction phase of the projects in 2009; the number of school projects to which this funding applies; and if he will make a statement on the matter. [9818/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

216 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget expended on furniture for primary schools in 2009; the number of schools that received such funding; and if he will make a statement on the matter. [9819/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

217 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget projected to be spent on the provision of prefabricated accommodation in primary schools in 2010; and if he will make a statement on the matter. [9820/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

218 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget projected to be spent on the provision of school sites for primary schools in 2010; and if he will make a statement on the matter. [9821/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

220 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget projected to be spent on the construction of major capital projects in primary schools during the construction phase of the projects in 2010; and if he will make a statement on the matter. [9823/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

223 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding expended on the summer works scheme in post-primary schools in 2009; the number of schools that received this funding; and if he will make a statement on the matter. [9826/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

224 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding expended on the provision of the minor works grant in post-primary schools in 2009; and if he will make a statement on the matter. [9827/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

225 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget expended on the provision of emergency funding to post-primary schools in 2009; the number of schools that received this funding; and if he will make a statement on the matter. [9828/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

226 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget expended on the provision of prefabricated accommodation in post-primary schools in 2009; the number of schools that received this funding; and if he will make a statement on the matter. [9829/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

227 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget expended on the provision of school sites for post-primary schools in 2009; the number of schools expected to be built on these sites; and if he will make a statement on the matter. [9830/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

228 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget expended on architectural plans and design teams for post-primary school building projects in 2009; the number of school projects to which this funding applies; and if he will make a statement on the matter. [9831/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

229 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget expended on the construction of post-primary schools in the construction phase of building projects in 2009; the number of school projects to which this funding applies; and if he will make a statement on the matter. [9832/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

230 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget expended on furniture for post-primary schools in 2009; the number of schools that received such funding; and if he will make a statement on the matter. [9833/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

231 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding projected to be spent on the summer works scheme in primary schools in 2010; the number of schools expected to receive this funding; and if he will make a statement on the matter. [9834/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

232 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding projected to be expended on the provision of the minor works grant in primary schools in 2010; and if he will make a statement on the matter. [9835/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

233 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget set aside for emergency funding to primary schools in 2010; and if he will make a statement on the matter. [9836/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

234 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget projected to be spent on furniture for primary schools in 2010; and if he will make a statement on the matter. [9837/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

236 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding expended on the summer works scheme in post-primary schools in 2009; the number of schools that received this funding; and if he will make a statement on the matter. [9839/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

237 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding expended on the provision of the minor works grant in post-primary schools in 2009; and if he will make a statement on the matter. [9840/10]

Amharc ar fhreagra

Freagraí scríofa

I propose to take Questions Nos. 209 to 218, inclusive, 220, 223 to 234, inclusive, 236 and 237 together.

The information on capital expenditure in the Primary and Post-Primary sectors in respect of the various sub-programmes that constitute the School Building Programme is summarised in the attached tabular format.

The total expenditure on the primary and post primary capital subhead was €328.9m and €197m respectively, utilised across a range of sub-programmes in the School Building Programme.

The bulk of expenditure on large scale projects relates to the 26 primary school projects and the 7 post-primary school projects that reached practical completion in 2009. In addition to the completed projects expenditure was also incurred on a further 19 large scale primary school projects and a further 5 large scale post-primary school projects that were on site during 2009, the majority of which are expected to be completed this year. Expenditure was also incurred on projects that reached practical completion in earlier years and on which outstanding project and fee balances were due. Furthermore, payments also issued on fees as design work on the various stages of projects in architectural planning was completed and approved.

The Deputy will appreciate that the site acquisition process can at times be a lengthy process subject to negotiations and legal formalities which are generally beyond the direct control of my Department and as such the site acquisition programme lends itself more readily to a multi annual process. In relation to 2009, I can advise that the Department directly concluded transactions, not including those undertaken by the VECs, in relation to 9 primary school sites and 2 post-primary school sites.

Under the Permanent Accommodation and Small Schemes 2005-2007 a total of 111 primary school projects and 8 post-primary school projects were completed in 2009. Expenditure on these devolved schemes while primarily on the completed projects was also applicable to a further 25 primary projects and 5 post-primary projects that were on site in 2009 but were not completed by year end.

Applications for additional accommodation are received by the Department throughout the year and in 2009 a total of 194 such applications in the primary sector and 47 such applications in the post-primary sector were approved. Expenditure was incurred on projects approved in either 2008 or 2009 as they commenced on site and/or reached completion. Each year schools apply for funding to the Department to carry out various emergency works and in 2009 a total of 545 emergency applications in the primary sector and 327 emergency applications in the post-primary sector were approved. Expenditure was incurred on these emergency works approved in either 2009 or in earlier years as works commenced and/or reached completion. 825 primary schools and 129 post-primary schools received approval for loose furniture and equipment in 2009. The expenditure incurred relates mainly to the 2009 approvals although a small number of approvals from earlier years were also funded in 2009.

A total of 824 school small and medium scale projects benefiting 650 primary schools and 358 school small and medium scale projects benefiting 317 post-primary schools were approved in 2009 under the Summer Works Scheme. The expenditure in 2009 relates mostly to these projects although a small number of projects approved in earlier years were also funded.

The Minor Works Grant in respect of the academic year 2009/2010 issued in November 2009 to 3,242 primary schools. The special pupil element of the 2008/2009 Minor Works Grant issued in July 2009.

School Building Programme 2010

The capital allocation for the Primary and Post-Primary sectors in 2010 is €578.8m. The Primary sector allocation is €378.8m and the Post-Primary is €200m. On 16 February I announced the 2010 large scale school building programme. 52 school projects (37 Primary and 15 Post-Primary) are to advance to tender and construction and 51 school building projects (44 Primary and 7 Post-Primary) will appoint design teams this year. Approval was given for 7 new primary schools to open in September in rapidly developing areas.

Arising from earlier school building programme announcements there are 30 large scale projects (23 Primary and 7 Post-Primary) under construction at present. 27 large scale projects (19 Primary and 8 Post-Primary) are due to commence construction during the first half of the year with a further 14 projects (10 Primary and 4 Post-Primary) due to go on site as soon as possible. Payments will issue on fees for other projects already in architectural planning.

Expenditure on large scale projects in 2010 is expected to be in the region of €250m. The allocation for the Summer Works Scheme 2010 will be on the same scale as 2009 and will facilitate the completion of over 1,000 small and medium scale building works. In addition, funding will also issue to applicant schools in respect of new water conservation measures. Expenditure on the Summer Works Scheme 2010 and on commitments arising from earlier years will be in the region of €110m. An allocation of €28m has been set aside for the Minor Works grant. Throughout the year capital funding will be available for a range of programmes including the completion of the Permanent Accommodation and Small School Schemes, the completion of the Energy Efficiency Scheme, the provision of furniture and equipment, the continuation of the remediation programmes (asbestos, radon and mould), emergency works, miscellaneous items, additional accommodation (prefabricated and permanent) and site acquisitions as they arise. Expenditure on these programmes is expected to cost €190m in 2010.

I should emphasise that, depending on the rate of progress of the various components of the programme, adjustments may be made throughout 2010. These adjustments may arise in the context of the on-going monitoring of the programme undertaken by my Department in the normal course of events.

School Building Programme 2009 — Expenditure Summary

Sub-Programmes

Primary

Post-Primary

€m

€m

Large Scale Projects

104.809

62.369

Site Purchases

24.63

24.806

Pas And Sss Schemes 2005-2007

33.78

2.586

Additional Accommodation

30.1

9.265

Emergency Works

35.109

32.187

Remediation

5.268

3.575

Furniture And Equipment

4.233

4.452

Summer Works Scheme

53.198

50.317

Minor Works Grant

29.161

0

Energy Efficiency Scheme

7.306

3.016

Curriculum, Health & Safety Grants

0

3.346

VEC HQ Accommodation

0

0.656

Miscellaneous

1.352

0.451

Total

328.946

197.026

Brian Hayes

Ceist:

219 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget projected to be spent on architectural plans and design teams for primary school building projects in 2010; and if he will make a statement on the matter. [9822/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

238 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget expended on the provision of emergency funding to post primary schools in 2009; the number of schools that received this funding; and if he will make a statement on the matter. [9841/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

239 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget expended on the provision of prefabricated accommodation in post primary schools in 2009; the number of schools that received this funding; and if he will make a statement on the matter. [9842/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

240 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget expended on the provision of school sites for post primary schools in 2009; the number of schools expected to be built on these sites; and if he will make a statement on the matter. [9843/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

241 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget expended on architectural plans and design teams for post primary school building projects in 2009; the number of school projects to which this funding applies; and if he will make a statement on the matter. [9844/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

242 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget expended on the construction of post primary schools in the construction phase of building projects in 2009; the number of school projects to which this funding applies; and if he will make a statement on the matter. [9845/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

243 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget expended on furniture for post primary schools in 2009; the number of schools that received such funding; and if he will make a statement on the matter. [9846/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

244 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding projected to be spent on summer works scheme in post primary schools in 2010; the number of schools expected to receive this funding; and if he will make a statement on the matter. [9847/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

245 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding projected to be expended on the provision of the minor works grant in post primary schools in 2010; and if he will make a statement on the matter. [9848/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

246 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget set aside for emergency funding to post primary schools in 2010; and if he will make a statement on the matter. [9849/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

247 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget projected to be spent on the provision of prefabricated accommodation in post primary schools in 2010; and if he will make a statement on the matter. [9850/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

248 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget projected to be spent on the provision of school sites for post primary schools in 2010; and if he will make a statement on the matter. [9851/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

249 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget projected to be spent on architectural plans and design teams for post primary building projects in 2010; and if he will make a statement on the matter. [9852/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

250 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget projected to be spent on the construction of major capital projects in post primary schools during the construction phase of the projects in 2010; and if he will make a statement on the matter. [9853/10]

Amharc ar fhreagra

Brian Hayes

Ceist:

251 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget projected to be spent on furniture for post primary schools in 2010; and if he will make a statement on the matter. [9854/10]

Amharc ar fhreagra

I propose to take Questions Nos. 219 and 238 to 251, inclusive, together.

School Building Programme 2009 — Expenditure Summary

Sub-Programmes

Primary

Post-Primary

€m

€m

Large Scale Projects

104.809

62.369

Site Purchases

24.63

24.806

Pas And Sss Schemes 2005-2007

33.78

2.586

Additional Accommodation

30.1

9.265

Emergency Works

35.109

32.187

Remediation

5.268

3.575

Furniture And Equipment

4.233

4.452

Summer Works Scheme

53.198

50.317

Minor Works Grant

29.161

0

Energy Efficiency Scheme

7.306

3.016

Curriculum, Health & Safety Grants

0

3.346

Vec Hq Accommodation

0

0.656

Miscellaneous

1.352

0.451

Total

328.946

197.026

Question No. 220 answered with Question No. 209.

Brian Hayes

Ceist:

221 Deputy Brian Hayes asked the Minister for Education and Science the amount of funding from the capital budget expended on information and communication technology in primary schools in 2009; the number of schools that received such funding; and if he will make a statement on the matter. [9824/10]

Amharc ar fhreagra

In November last year I published the ‘Smart Schools = Smart Economy' report, which is the new action plan for integrating ICT in schools. As a first step in implementing the recommendations of the report, €22m in ICT grants was issued to primary schools. In total 3,215 schools received funding under this scheme. In addition to this, €1.5 million of Dormant Account funding was allocated for 100 DEIS Urban Band 1 schools towards the purchase of ICT equipment to assist them to achieve Digital Schools status. Funding for ICT infrastructure is also provided to schools in the context of large scale building projects, and is calculated on the basis of a provision of €5,000 per classroom.

I have committed €50 million in capital expenditure for 2010 and look forward to working with schools to further improve the ICT infrastructures in place.

Barr
Roinn