Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Schools Building Projects

Dáil Éireann Debate, Wednesday - 9 June 2010

Wednesday, 9 June 2010

Ceisteanna (366)

Pat Breen

Ceist:

366 Deputy Pat Breen asked the Tánaiste and Minister for Education and Skills further to Parliamentary Question No. 1146 of 3 November 2009, if there has been any progress on a project (details supplied); and if she will make a statement on the matter. [24675/10]

Amharc ar fhreagra

Freagraí scríofa

As the Deputy is aware, my Department has received an application for large scale capital funding from the school to which he refers. The application has been assessed in accordance with the published prioritisation criteria for large scale building projects and assigned a Band 2 rating. Information in respect of the current school building programme along with all assessed applications for major capital works, including the project referred to by the Deputy, are now available on my Department's website at www.education.ie.

The priority attaching to individual projects is determined by published prioritisation criteria, which were formulated following consultation with the Education Partners. There are four band ratings under these criteria, each of which describes the extent of accommodation required and the urgency attaching to it. Band 1 is the highest priority rating and Band 4 is the lowest. Documents explaining the band rating system are also available on my Department's website.

The progression of all large scale building projects, including this project, from initial design stage through to construction phase will be considered in the context of my Department's multi-annual School Building and Modernisation Programme. However, in light of current competing demands on the capital budget of the Department, it is not possible to give an indicative timeframe for the progression of the project at this time.

Barr
Roinn