Dáil Éireann Debate, Thursday - 11 November 2010

Thursday, 11 November 2010

Ceisteanna (120)

Denis Naughten

Ceist:

116 Deputy Denis Naughten asked the Minister for Finance further to Parliamentary Question No. 132 of 23 June 2009, the updated figures for the number of public servants decentralised to date in each project concerned; when the final transfer will be completed; and if he will make a statement on the matter. [42232/10]

Amharc ar fhreagra

Freagraí scríofa

A total of 3,407 staff have decentralised to 37 locations since the commencement of the programme.

Table 1 gives details of 31 projects in respect of which permanent accommodation has been procured or provided. A total of 2,232 staff have moved to take up positions at those locations.

Table 2 gives details of a further 3 sites where the contractual arrangements for the provision of permanent accommodation are already in place or are under active consideration. A total of 457 staff have already moved to advance offices in respect of these projects.

Table 3 gives details of 57 projects in 41 locations where contractual commitments for the provision of permanent accommodation have not yet been entered into. Advance parties totalling 718 staff are in place in temporary accommodation in respect of 16 of these projects. As already announced, decisions on the timing of implementation of the balance of these projects are deferred pending a review in 2011 in light of budgetary developments. The current economic environment and policies affecting overall public service numbers will impact on the timeframe for the completion of each project and the transfer of further staff to these locations.

Table 1: Decentralisation Projects where property is already completed

Location

Organisation

Total posts to be decentralised

Staff moved to decentralising location to 10 November 2010

Athlone

Education & Skills

88

88

Ballina

Road Safety Authority

62

62

Buncrana

Social Protection

102

100

Carrick-on-Shannon (Phase I)

Social Protection

159

159

Clonakilty

Agriculture Fisheries & Food

86

85

Clonakilty

BIM

90

20

Clonakilty

Sea Fisheries Protection Authority

47

47

Cork

HIQA

100

47

Gaoth Dobhair

Foras Na Gaeilge

5

5

Killarney

Tourism Culture & Sport

103

79

Kilrush

Office of the Revenue Commissioners

57

57

Limerick

Foreign Affairs

134

134

Listowel

Office of the Revenue Commissioners

52

52

Longford

Irish Prison Service

133

133

Loughrea

Road Safety Authority

40

40

Loughrea

Transport

10

10

Naas

IAASA

13

12

Na Forbacha

Community Equality and Gaeltacht Affairs

13

12

Navan

Coroners Service

4

4

Navan

Garda Civilian HR Division

38

38

Navan

National Property Services Regulatory Authority

9

9

Navan

Office of the Director of Probation Service

15

15

Navan

Office of the Revenue Commissioners

100

100

Newbridge

Defence

201

162

Newbridge

Defence Forces

43

55

Newcastlewest

Office of the Revenue Commissioners

52

52

Sligo

Social Protection

88

72

Tipperary Town

Private Security Agency

32

32

Trim

Office of Public Works

334

240

Tullamore

Finance

130

122

Wexford

Environment Heritage & Local Government

270

189

Total

2,610

2,232

Table 2: Priority Decentralisation Projects Approved by Government to Proceed

Location

Organisation

Total posts to be decentralised

Staff moved to decentralising location at 10 November 2010

Property Update

Portlaoise (HQ location)

Community Equality and Gaeltacht Affairs

595

317

Following the decision in December 2009 not to proceed with the PPP Midlands Bundle the Portlaoise project is to proceed on a traditional procurement basis.

Roscommon

Property Registration Authority

230

77

The PRA is expected to move to the building early in the New Year,

Tipperary Town

Justice and Law Reform

186

63

Construction Work due to start early December 2010

Total

1,011

457

Table 3: Decentralisation Projects Deferred, Pending a Review in 2011*

Location

Organisation

Staff moved to decentralising location to 10 November 2010

Moves Deferred

Arklow

NSAI

124

Athlone

Higher Education Authority

64

Athy (advance party in place)

Office of Revenue Commissioners

73

180

Ballinasloe

National Roads Authority

110

Birr (advance party in place)

FÁS

20

378

Carlow (advance party in place)

Enterprise Trade and Innovation

103

257

Carrickmacross

Social Protection

85

Carrick on Shannon

Central Fisheries Board

54

Carrick on Shannon (Phase II)

Social Protection

90

Cavan (advance party in place) — HQ

Communications Energy & Natural Resources

57

244

Cavan/Portlaoise/Galway

HIQA

80

Charlestown (advance party in Tubbercurry)

Community Equality & Gealtacht Affairs

100

64

Claremorris (Phase I)

Office of Public Works

31

104

Claremorris (Phase II)

Office of Public Works

38

Clifden (advance party in place)

Pobal

25

17

Currage

Defence Forces

413

Donegal

Socail Protection

258

Drogheda

Transport

37

Drogheda

Citizens Information Board

49

Drogheda

Local Government Computer Service Board

101

Drogheda

Railway Safety Commission

16

Drogheda

Social Protection

499

Dundalk (advance party in place)

Sustainable Energy Ireland

11

23

Dungarvan

OSI

206

Edenderry

FETAC

44

Edenderry

HETAC

34

Edenderry

NQAI

18

Enniscorthy

Bord Bia

76

Fermoy

Agriculture Fisheries & Food

100

Gaoth Dobhair

Foras na Gaeilge

25

Kanturk

Office of Public Works

88

Kildare

Office of the Revenue Commissioners

380

Kildare

Finance — CMOD

30

Kilkenny

Environment Heritage & Local Government

62

Kilkenny

Arts Council

49

Killarney

Irish Sports Council

31

Macroom

Agriculture Fisheries & Food

100

Mallow

Fáilte Ireland

163

Mitchelstown

CIÉ Group

200

Monaghan

Combat Poverty Agency

25

Mullingar

Education & Skills

7

290

Naas

Health Service Executive

300

New Ross

Environment Heritage & Local Government

125

Portarlington (advance party)

Data Protection Commissioner

23

0

Portarlington (advance party in Portlaoise)

Equality Tribunal (civil service)

8

34

Portarlington (advance party in Portlaoise)

NCCA (civil service)

12

25

Portarlington

NEWB

14

Roscrea (advance party in place)

Equality Authority (civil service)

16

25

Roscrea

Garda Ombudsman Commission

23

Shannon (advance party in place)

Enterprise Ireland**

66

226

Shannon

Irish Aviation Authority

102

Thomastown (advance party in Kilkenny)

Health & Safety Authority

33

83

Thurles (advance party in place)

Garda Headquarters CGVU & FCPS

133

133

Waterford

Environment Heritage & Local Government

225

Wexford

National Building Agency

63

Youghal

Public Appointments Service

100

Youghal

Valuation Office

100

Total

718

6,784

*This Review will take account of the impact of the Rationalisation of State Agencies.

**Including 40 existing Shannon Development and EI posts located in Shannon as part of a parallel process.